RV Garage

Client Name: Tom and Susie Petrizzio

Start Date:
Project Sqft Total:


Project Description:
Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Excavation and Backfill Tycon $114,461.50 $ $ $0.00
Footing and Foundation FYN $38,300.00 $ $ $0.00
Additional Rebar NWC $2,500.00 $ $ $0.00
Foundation Plastering FYN $2,500.00 $ $ $0.00
Material Handling NWC $2,400.00 $ $ $0.00
Lumber Rough SunPro $30,000.00 $ $ $0.00
Trusses SunPro $0.00 $ $ $0.00
Carpentry Rough JRC $30,300.00 $ $ $0.00
Windows / Glass Doors Sierra Pacific $5,400.00 $ $ $0.00
Exterior Siding Material Innovative Construction $18,065.00 $ $ $0.00
Masonry FYN $0.00 $ $ $0.00
Soffit / Fascia North West $0.00 $ $ $0.00
Electrical / Home Automation Pauls Electric service $10,000.00 $ $ $0.00
Electrical Fixtures Owner $3,500.00 $ $ $0.00
Heating HVAC Paul’s Heating $10,000.00 $ $ $0.00
Roofing L & M North West $0.00 $ $ $0.00
Gutter North West $0.00 $ $ $0.00
Insulation Pick’s $11,307.00 $ $ $0.00
Drywall Jose Torres $8,500.00 $ $ $0.00
Painting Interior MC Baldwin $10,000.00 $ $ $0.00
Lumber Finish SunPro $2,500.00 $ $ $0.00
Carpentry Finish Wasatch Group $5,600.00 $ $ $0.00
Doors Exterior / Interior Frontier woodworks $1,500.00 $ $ $0.00
Garage Door 5 Star $20,000.00 $ $ $0.00
Hardware SunPro $1,500.00 $ $ $0.00
Winter Costs NWC $3,000.00 $ $ $0.00
Landscaping NWC $0.00 $ $ $0.00
Site Control / Clean-up NWC $7,500.00 $ $ $0.00
Final Clean NWC $3,000.00 $ $ $0.00
Dumpster NWC $2,500.00 $ $ $0.00
Chemical Toilet NWC $2,500.00 $ $ $0.00
General Labor NWC $5,000.00 $ $ $0.00
Totals
Final Estimate:

$351,833.50

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00

Project Images
Attachments




 

 

Click Here to Print This Page