40 x 20 Barn
Client Name: Brent and Linda Flynn
Start Date:
Project Sqft Total:
Project Description:
Budget Breakdown
| Description | Vendor (Private) | Estimated Cost | Actual Cost | Current Paid | Amount Due | Notes (Private) | Description |
|---|---|---|---|---|---|---|---|
| Carpentry Rough | NWC | $0.00 | $ | $ | $0.00 |
There will be a cost to extend the eyebrow… Not sure what that will be but not much… |
|
| Windows / Glass Doors | Sierra Pacific Windows | $4,250.02 | $ | $ | $0.00 |
The 3 additional windows… |
|
| Exterior Siding Material | Innovative Construction | $16,318.50 | $ | $ | $0.00 |
Estimate $28450.00 and you have already paid $12,131.50 of this for a deposit… |
|
| Soffit / Fascia | North West Roffing | $4,252.00 | $ | $ | $0.00 | ||
| Siding Labor | Innovative Construction | $0.00 | $ | $ | $0.00 |
Included in siding material price… |
|
| Electrical / Home Automation | Pauls electric service | $8,000.00 | $ | $ | $0.00 |
This is a budget number for the electrical.. The budget number will change plus or minus depending on what is actually wired in the barn per owners request.. |
|
| Electrical Fixtures | owner | $0.00 | $ | $ | $0.00 |
Home owner will provide… |
|
| Roofing L & M | North West Roofing | $15,757.00 | $ | $ | $0.00 |
Does not include the eyebrow… |
|
| Insulation | Empire Insulation | $12,863.00 | $ | $ | $0.00 |
The contractor said he would credit you back for anything he uses of your insulation that you have on site… |
|
| Drywall | Tores drywall | $11,300.00 | $ | $ | $0.00 |
He will have to use 5/8″ drywall because of the upstairs for code… |
|
| Painting Exterior | Innovative Construction | $0.00 | $ | $ | $0.00 |
Included in siding material bid… |
|
| Doors Exterior / Interior | Frontier woodworks | $1,520.56 | $ | $ | $0.00 |
Plus tax… and labor to install… |
|
| Garage Door | Five Star | $15,460.00 | $ | $ | $0.00 | ||
| Hardware | NWC | $700.00 | $ | $ | $0.00 |
Budget number for labor and material to buy and install… |
|
| Overhead / General Expenses | NWC | $904.21 | $ | $ | $0.00 |
1 % O/GE |
|
| General Contractor Fee | NWC | $13,563.16 | $ | $ | $0.00 |
15 % GC fee… |
Totals
Final Estimate:$104,888.45 |
Actual Total-to-Date:$0.00 |
Total Amount Paid:$0.00 |
Current Amount Due:$0.00 |