Morley Residence

Client Name: Zachary & Catherine Morley

Start Date: June 1, 2023
Project Sqft Total: 3768


Project Description:

Main level Sq Ft 1821
Upper level Sq Ft 1107
Bonus level Sq Ft 840
Garage Sq Ft 840

Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Various $22,000.00 $16,787.38 $16,787.38 $0.00

Plan printing $103.60, $487.67, $242.64, $242.64, $42.53 Stormwater NOI fee $150.00, Fire District fee $702.04, Legend Drilling $387.50, Summit County $500.00, Tycon $ 2,410.00. Summit County $40.00, $17,280.40, $100.00.
Bond Release CREDIT $5,901.64

Excavation and Backfill Tycon $73,812.50 $112,652.70 $112,652.70 $0.00

Includes water line to well, septic system and base for driveway..
THIS IS A BUDGET NUMBER… See estimate
Tycon $13,586.00, $56,177.00, $25,292.47

Footing and Foundation FYN Cuellar $114,204.00 $114,204.00 $114,204.00 $0.00

There most likely will be additional costs for winter..
FYN $42,214.00 FOOTINGS FYN $71,990.00

Foundation Weather Proofing Rocky Mountain Waterproofing $13,350.00 $935.00 $935.00 $0.00

Please see bid for options … Rocky Mountain Waterproofing paid $935.00
40 mil Waterproofing membrane (foundation) $870.00
Footing strip drain $800.00
Under slab 2″ rigid foam labor and material $9900.00
Vapor barrier 15 mil polyethylene $1780.00

Additional Rebar NWC $5,000.00 $ $ $0.00
Foundation Plastering FYN $3,500.00 $2,400.00 $2,400.00 $0.00

Budget Number Only..

Fill / Gravel Tycon $0.00 $ $ $0.00

We may need more material for the road work…

Steel Connections J and J $3,500.00 $2,571.84 $2,571.84 $0.00

Budget Number Only..
J&J Fabrication $2,410.88, Home Depot $160.96

Material Handling NWC $10,800.00 $990.00 $990.00 $0.00

Budget Number for equipment to handle material through out the duration of the project..
NWC $990.00

Lumber Rough Sunpro $60,000.00 $65,793.11 $65,793.11 $0.00

Sunpro quote Budget Number..
Sunpro $37,240.31, $19,616.01, $7,304.46, $67.57, $1564.76 (Timber trusses)

Trusses Sunpro $22,000.00 $30,856.00 $30,856.00 $0.00

Budget Number Only..
Sunpro $30,856.00

Carpentry Rough JRC Custom Homes $73,936.00 $94,283.20 $94,283.20 $0.00

Additional cost charged at $65.00 per man hour if needed.. For snow removal, post and beam work on front and gable ends, and any drops needed…
JRC $27,600.00, $33,652.20, $27,936.00, $5,095.00 (Timber Trusses)

Windows / Glass Doors Sierra Pacific Windows $55,500.00 $56,554.00 $56,554.00 $0.00

Sierra Pacific Windows $46,054.00, $10,500.00

Exterior Siding Material Innovative Construction $14,105.00 $20,092.21 $20,092.21 $0.00

Sunpro Ghostwood Siding $18,054.00 (material)
Innovative Construction 25% down $2,388.75, Sunpro $17,703.46

Masonry FYN Cuellar $22,000.00 $23,441.87 $23,441.87 $0.00

Budget for inside fireplace.. Based on 400 Sq.Ft. of rock..
FYN = $18,909.00 The Home Depot $47.87

Soffit / Fascia Northwest $14,556.00 $11,198.00 $11,198.00 $0.00

North West $9.948.00, North West $1,250.00

Siding Labor Innovative Construction $19,725.00 $26,446.25 $26,446.25 $0.00

Innovative Construction 25% down $5,456.25, $20,990.00

Plumbing MVPH $40,121.00 $47,112.97 $47,112.97 $0.00

See estimate for the budget on the plumbing fixtures.. Price may change depending on what is actually installed..
MVPH $21,200.00, $25,912.97

Electrical / Home Automation Paul’s Electric $60,019.60 $64,083.27 $64,083.27 $0.00

Junction Electric $32,185.48, $24,742.90
Electrical Service – Junction Electric $7,154.89

Electrical Fixtures NWC $10,000.00 $ $ $0.00

Budget Number Only.. Owner or designer will order and deliver to job site..

Electronics Mountain Top Home Audio $33,598.43 $9,682.69 $9,682.69 $0.00

Optional, look at bid to discuss..
Mountain Top = $3,500.00, $7,038.80 CREDIT -$856.11

Heating HVAC Paul’s Heating and A/C $44,550.00 $45,908.71 $45,908.71 $0.00

Paul’s Heating A/C $35,085.00, $7,490.00 Unit Heater in Garage $2,775.00 Thermostats $558.71

Radiant Heat MVP&H $0.00 $ $ $0.00

Optional ???

Fire Sprinklers NWC $0.00 $ $ $0.00

Not Needed..

Roofing L & M North West Roofing $23,392.00 $38,513.00 $38,513.00 $0.00

Shingle roof $17,536.00, Metal roof $5,856.00
North West $16,690.00, $13,843.00
North West Snow Retention $7,980.00

Fireplaces Alpine Fireplace $23,733.95 $20,643.50 $20,643.50 $0.00

Direct vent Marquis model $14,109.20 See thru wood/gas $23,733.95
Alpine Gas Fireplace $15,093.20, $5,550.30

Chimney Cap Northwest $2,800.00 $ $ $0.00

Budget Number, all depends on what it ends up being..

Gutter Northwest $6,035.00 $6,035.00 $6,035.00 $0.00
Heat Tape Pauls Electric Service $0.00 $11,495.00 $11,495.00 $0.00

Will need to install before next winter..
Summit Electric $11,495.00

Insulation Hansen All Seasons $25,739.00 $25,285.00 $25,285.00 $0.00

This bid could change depending on what we actually do..
Hansen Insulation $8,351.23, $3,362.60, $11,759.25, $1,811.92

Drywall Torres Drywall $24,300.00 $24,300.00 $24,300.00 $0.00
Painting Interior MC Baldwin Painting $58,132.00 $57,485.67 $57,485.67 $0.00

House $33,672.00
Garage $6,300.00
Bonus $9,660.00
Exterior doors budget only $1,500.00
Post and beam staining budget number only $1,500.00
Epoxy garage floors $5,500.00
Ace Hardware $28.67,
MC Baldwin Painting $44,832.00, $12,625.00

Painting Exterior Innovative Construction $15,780.00 $18,225.00 $18,225.00 $0.00

Innovative Construction 25% down $2,545.00, $10,180.00. Baldwin $5,500.00

Lumber Finish Sunpro $25,000.00 $11,221.95 $11,221.95 $0.00

Budget Number.. Sunpro $509.83, 1,555.07, The Home Depot $1,425.11, Frontier Doors $7,731.94

Carpentry Finish Wasatch Development $32,452.00 $43,481.50 $43,481.50 $0.00

Buildworx $34,146.50, $9,334.00

Closets / Shelving / Built-ins Sunpro $6,500.00 $6,500.00 $6,500.00 $0.00

Budget Number Labor and Material.. Buildworx $6,500.00

Doors Exterior / Interior Frontier Woodworks $24,860.04 $29,049.34 $29,049.34 $0.00

Interior doors budget $12,310.04. Pocket Door-Sunpro $4,407.14. Doors $12,416.15, Barn Door Frontier Woodworks $1,821.55
Exterior door budget $12,550.0 This budget is for metal front entry door.. High Country Doors $4,502.25, $2251.13, $3,651.12

Garage Door 5 Star Building $9,850.00 $10,765.00 $10,765.00 $0.00
Railings NWC $5,000.00 $ $ $0.00

Budget Number Only… Price may change depending on style installed..

Hardware Sun Pro $4,500.00 $2,114.27 $2,114.27 $0.00

Budget Number..

Hardware Labor Wasatch Group $3,754.00 $ $ $0.00
Cabinets A&A Cabinet $61,500.00 $63,650.00 $63,650.00 $0.00
Countertops MaCorp $19,975.00 $19,800.00 $19,800.00 $0.00

Budget for all countertops throughout house..
MaCorp = $10,690.00, $9,110.00

Mirrors / Bath Enclosures NWC $11,500.00 $6,829.00 $6,829.00 $0.00

Budget Number Only…
Beehive Glass $6,829.00

Tile Tubs / Showers MaCorp $23,481.25 $31,245.59 $31,245.59 $0.00

See Estimate..
MaCorp = $18,492.52, $18,748.08, $4,689.99 CREDIT $10,685.00

Floors Tile / Stone $0.00 $ $ $0.00

Included in Tile Tubs/Showers estimate

Floors Wood MaCorp $15,532.50 $22,418.70 $22,418.70 $0.00

See Estimate ..
MaCorp= $12,566.84, $4,983.38, $4,868.48

Erosion Control Erosion Control Services $11,242.50 $1,690.00 $1,690.00 $0.00

Erosion Control $1,525.00, $165.00

Engineering / Surveying Epic $15,000.00 $17,732.17 $17,732.17 $0.00

Epic $4,900, $1,423.25, $1,986.75, $477.75, $720.17, $1,998.25, $328.50, $328.50, $219.00 Element Land Surveying $1,750, $800.00, $800.00, $850.00, $600.00, $550.00

Floors Carpet NWC $13,500.00 $10,443.86 $10,443.86 $0.00

Budget Number Only… Based on 2100 Sq.Ft. and 2 staircases… $50.00 a yard..
MaCorp $5,049.00, $5394.86

Appliances / Built-in Vacuum MLD $25,000.00 $ $ $0.00

Budget Number Only.. Owner needs to pick out the appliances..

Appliance Installation MLD $3,500.00 $ $ $0.00

Budget Number Only.. Owner needs to pick out the appliances..

Flatwork Exterior Material FYN Cuellar $75,509.00 $69,585.75 $69,585.75 $0.00

Labor and Material .. Look at Estimate for what is included.. Price may change depending on Sq.Ft. of concrete installed..
FYN= Garage floor $18,729.00, Porches $22,480.00, $27,626.75
Saw Jockey $750.00

Driveway NWC $0.00 $ $ $0.00

This will need to be addressed next spring…

Final / Pre-Landscaping Grading Tycon $0.00 $ $ $0.00

Included in Tycon’s estimate..

Winter Costs NWC $30,000.00 $1,495.00 $1,495.00 $0.00

Needed when weather is bad… BUDGET ONLY.. ALL BASED ON UNKNOWN WEATHER
JRC $1,495.00

Site Control / Clean-up NWC $7,500.00 $3,135.00 $3,135.00 $0.00
Final Clean NWC $7,500.00 $3,844.50 $3,844.50 $0.00

Budget Number Only.. Construction final house cleaning, window cleaning and air duct system cleaning..
Titan $1,383.50 Crystal Clean Vents $897.00 All We Can Do $1,564.00

Dumpster Honey Bucket $7,500.00 $5,717.49 $5,717.49 $0.00

Honey Bucket $503.98, $888.10, $371.40, $888.50, $560.00, $1,678.78, $826.73

Chemical Toilet Honey Bucket $3,600.00 $2,384.46 $2,384.46 $0.00

Honey Bucket $260.40, $171.42, $174.00, 273.40, $170.90, $153.80, $152.77, $567.85, $266.90, $160.02, $33.00

General Labor NWC $7,500.00 $1,234.36 $1,234.36 $0.00

Saw Jockey $475.00, Legend Drilling $425.00, NWC $334.36

Monthly Management Fee NWC $54,000.00 $48,000.00 $48,000.00 $0.00

18 months updated 10/7

Overhead / General Expenses NWC $14,137.43 $13,289.03 $13,289.03 $0.00

1% Fee above cost to build..

General Contractor Fee NWC $169,649.13 $159,468.00 $159,468.00 $0.00

12% Fee above cost of build..

Totals
Final Estimate:

$1,585,232.33

Actual Total-to-Date:

$1,533,070.34

Total Amount Paid:

$1,533,070.34

Current Amount Due:

$0.00

Project Images
Attachments




 

 

Click Here to Print This Page