Rydalch Residence

Client Name: Lucas & Haley Rydalch

Start Date: June 14, 2024
Project Sqft Total:


Project Description:

Main Level Sq Ft 1,356
Loft Sq Ft 672
Basement Sq Ft 1,248
Garage Sq Ft 898
Covered Deck 806

Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Oakley City $0.00 $ $ $0.00

Owner will provide..

Excavation and Backfill Tycon $42,137.00 $ $ $0.00

Includes french drain, septic system and water line. THIS IS A BUDGET NUMBER ONLY

Footing and Foundation FYN Cuellars $127,451.00 $ $ $0.00
Foundation Weather Proofing Rocky Mountain Waterproofing $3,800.00 $ $ $0.00

Check estimate for options..

Foundation Plastering FYN $0.00 $ $ $0.00

Not needed for code..

Fill / Gravel Tycon $8,000.00 $ $ $0.00

May need for drive way prep or flat work prep..

Steel Connections NWC $3,000.00 $ $ $0.00

Budget only..

Material Handling NWC $0.00 $ $ $0.00

We may have some cost here unless owner takes care of it..

Lumber Rough Sunpro $67,323.60 $ $ $0.00

This number has a built in contingency already added in..

Trusses Sunpro $16,012.50 $ $ $0.00
Carpentry Rough JRC Custom Homes $57,982.00 $ $ $0.00

Includes timber work..

Windows / Glass Doors Sierra Pacific $29,824.00 $ $ $0.00
Exterior Siding Material Sunpro $32,378.16 $ $ $0.00

The Budget is based on a pre stained wood side material only..
Budget for a smart siding with exterior painting is $47,460.00

Masonry FYN $0.00 $ $ $0.00

There is no rock bid for the chimney..

Soffit / Fascia North West Roofing $17,400.00 $ $ $0.00
Siding Labor Innovative Construction $20,000.00 $ $ $0.00

Labor for installing of the wood siding..

Plumbing MVPH $33,796.78 $ $ $0.00

Look at estimate to see the cost of the soft water system ($3000.00) and the hot water recirculating system ($3500.00)

Plumbing Fixtures MVPH $0.00 $ $ $0.00

Check estimate for what the option there is for the finishes..

Electrical / Home Automation Owner $0.00 $ $ $0.00

Owner will provide..

Electrical Fixtures Owner $0.00 $ $ $0.00

Owner will provide..

Heating HVAC Paul’s Heating & A/C $19,500.00 $ $ $0.00

Check estimate to see what is included..

Roofing L & M North West Roofing $34,430.00 $ $ $0.00

All Metal option as per plans.. $55,100.00
Combo with shingles and metal option .. $34,430.00

Fireplaces Alpine Fireplace $9,607.85 $ $ $0.00

Wood Burning $9,607.85
Gas $6,493.00

Fireplace Feature Wall FYN $0.00 $ $ $0.00
Chimney Cap North West Roofing $0.00 $ $ $0.00
Gutter North West Roofing $6,630.00 $ $ $0.00

Custom 24 Gauge Metal $13,888
Aluminum $6,630.00

Insulation Hansen Insulation $22,862.00 $ $ $0.00
Drywall Torres Drywall $20,900.00 $ $ $0.00
Painting Interior Baldwin Painting $20,277.00 $ $ $0.00

Look at estimate to see what is included..

Lumber Finish Sunpro $6,549.10 $ $ $0.00
Carpentry Finish BuildWorx $0.00 $ $ $0.00

Owner will Install..

Closets / Shelving / Built-ins BuildWorx $0.00 $ $ $0.00

Owner will install..

Doors Exterior / Interior Frontier Doors $16,135.75 $ $ $0.00

Frontier – Solid core, paint grade $11,235.75
High Country Iron Doors $4,100.00
Exterior door $800.00

Garage Door Five Star Building $10,205.00 $ $ $0.00

Five Star Garage Doors $8,955.00
North West Roofing garage wrap $1,250.00

Railings NWC $6,500.00 $ $ $0.00

Budget number only..

Hardware Sunpro $3,000.00 $ $ $0.00

Locks $3,000

Hardware Labor BuildWorx $0.00 $ $ $0.00

Owner to install..

Cabinets A&A Cabinet $28,350.00 $ $ $0.00
Countertops MaCorp $8,550.00 $ $ $0.00
Mirrors / Bath Enclosures Owner $0.00 $ $ $0.00

Owner supply..

Tile Tubs / Showers MaCorp $16,660.42 $ $ $0.00
Floors Tile / Stone MaCorp $0.00 $ $ $0.00

Included in the Tile Tub / Shower bid..

Floors Wood MaCorp $20,893.50 $ $ $0.00
Floors Carpet MaCorp $3,500.00 $ $ $0.00

Budget for bedrooms and closets only..

Appliances / Built-in Vacuum MLD $15,000.00 $ $ $0.00

BUDGET NUMBER ONLY

Appliance Installation NWC $1,500.00 $ $ $0.00

BUDGET NUMBER ONLY

Flatwork Prep Tycon $0.00 $ $ $0.00

There is a budget of $1500.00 In Tycon’s bid to prep for this..

Flatwork Exterior Material FYN Cuellars $47,499.00 $ $ $0.00

Labor and material – Basement and exterior concrete

Driveway FYN Cuellars $16,430.00 $ $ $0.00

Price is based on a Sq Ft… Driveway 900 Sq ft at $13.00 and $2.50 for rebar..
Budget Number Sidewalk 160 Sq ft at $13.00 and $2.50 for rebar..

Winter Costs NWC $0.00 $ $ $0.00
Site Control / Clean-up NWC $0.00 $ $ $0.00
Final Clean NWC $5,000.00 $ $ $0.00

Budget for final house cleaning, duct cleaning and window cleaning

Dumpster NWC $0.00 $ $ $0.00
Chemical Toilet NWC $2,500.00 $ $ $0.00
General Labor NWC $5,000.00 $ $ $0.00

Only if needed..

Hazard Insurance Owner $0.00 $ $ $0.00

OWNER WILL PROVIDE..

Liability Insurance Owner $0.00 $ $ $0.00

OWNER WILL PROVIDE..

General Contractor Fee NWC $0.00 $ $ $0.00
Totals
Final Estimate:

$806,584.66

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00

Project Images
Attachments




 

 

Click Here to Print This Page