Stockley Barndominium

Client Name: Alex Stockley

Start Date:
Project Sqft Total:


Project Description:

Garage 2638 Sq Ft
Living 938 Sq Ft
Deck 488 Sq Ft
Lower Bath 62 Sq Ft

Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits $0.00 $ $ $0.00
Excavation and Backfill Tycon $29,840.00 $ $ $0.00

Includes excavation, septic and water line install

Footing and Foundation FYN Cuellars $49,710.00 $ $ $0.00
Foundation Plastering $0.00 $ $ $0.00
Fill / Gravel NWC $0.00 $ $ $0.00

May need this..

Steel Connections NWC $2,500.00 $ $ $0.00

If needed..

Lumber Rough Sunpro $39,288.75 $ $ $0.00

Budget number only..

Trusses Sunpro $12,254.50 $ $ $0.00
Carpentry Rough JRC $46,300.00 $ $ $0.00
Windows / Glass Doors Sierra Pacific $26,316.00 $ $ $0.00
Exterior Siding Material Innovative Con. $39,670.00 $ $ $0.00

Siding and Trim and exterior paint

Soffit / Fascia North West Roofing $11,100.00 $ $ $0.00
Siding Labor Innovative Con.. $0.00 $ $ $0.00

Included in siding material bid..

Plumbing MVPH $17,500.48 $ $ $0.00
Plumbing Fixtures MVPH $0.00 $ $ $0.00

Budget included in Plumbing bid..

Electrical / Home Automation Junction Electric $23,933.20 $ $ $0.00
Electrical Fixtures Owner $3,500.00 $ $ $0.00

Budget only..

Heating HVAC Paul’s Heating & A/C $17,500.00 $ $ $0.00
Roofing L & M Northwest Roofing $14,980.00 $ $ $0.00
Fireplaces Alpine Fireplace $0.00 $ $ $0.00

$2,303.00 for a gas fireplace if you want to add it…

Gutter Northwest Roofing $4,470.00 $ $ $0.00

Upper Roof $1,980.00
Lower Roof $2,490.00

Insulation Hansen Insulation $25,895.00 $ $ $0.00
Drywall Torres Drywall $25,500.00 $ $ $0.00
Painting Interior MC Baldwin Painting $11,000.00 $ $ $0.00

Main Living $11,000.0
Garage $7,714.00
Epoxy garage floor $15,828.00

Painting Exterior Innovative Con.. $0.00 $ $ $0.00

Included in siding material bid..

Lumber Finish Frontier woodworks $4,500.00 $ $ $0.00

Budget number..

Carpentry Finish Buildworx $4,004.00 $ $ $0.00
Closets / Shelving / Built-ins Buildworx $2,500.00 $ $ $0.00

Master closet labor and material budget number..

Doors Exterior / Interior Frontier Woodworks $4,920.11 $ $ $0.00

Add $7,500.00 for steel door to replace garage door in future game room on lower level.. There will be a credit on one of the garage door if we go this way..

Garage Door 5 Star Building $12,885.00 $ $ $0.00

Flush Panel = $12,885.00 With Windows $18,905.00

Railings J&J Fabrication $14,500.00 $ $ $0.00

Railing on both side of the staircase plus the front of the covered deck. 90/ft of railing. The cost for a basic metal rail powder coated and installed would be $13,500 + tax. The column schedule says there is a HSS4x4x1/4, but it’s not on plans.

Stairs $0.00 $ $ $0.00
Hardware SunPro $2,500.00 $ $ $0.00

Budget number..

Hardware Labor Buildworx $1,500.00 $ $ $0.00
Cabinets A&A Cabinets $24,700.00 $ $ $0.00

CLEAR ALDER/PAINT GRADE FOR THE KITCHEN AND VANITIES $24,700. LAUNDRY/MUD ROOM not included in the bid

Countertops MaCorp $7,870.00 $ $ $0.00
Mirrors / Bath Enclosures NWC $0.00 $ $ $0.00
Tile Tubs / Showers MaCorp $10,996.25 $ $ $0.00
Floors Tile / Stone $0.00 $ $ $0.00

Included in Tile estimate

Floors Wood MaCorp $9,106.00 $ $ $0.00
Deck System NWC $10,000.00 $ $ $0.00

This is a budget for weather proof deck and installing concrete.. Budget only..

$ $ $ $0.00
Floors Carpet MaCorp $1,880.00 $ $ $0.00
Appliances / Built-in Vacuum owner $12,000.00 $ $ $0.00

Budget only..

Appliance Installation $1,500.00 $ $ $0.00

Budget only..

Flatwork Exterior Labor FYN Cuellars Construction $40,969.95 $ $ $0.00

Garage floor..
Concrete Floor in Bardominium $35,819.95… $5,150.00 is the floor drain system…

Driveway Owner $0.00 $ $ $0.00

Nothing is in Budget for this..

Winter Costs $0.00 $ $ $0.00
Site Control / Clean-up Owner $0.00 $ $ $0.00

Owner must do..

Final Clean NWC $3,500.00 $ $ $0.00
Dumpster NWC $2,000.00 $ $ $0.00
Chemical Toilet NWC $1,500.00 $ $ $0.00
General Labor $0.00 $ $ $0.00
Monthly Management Fee $0.00 $ $ $0.00
Overhead / General Expenses $0.00 $ $ $0.00
General Contractor Fee NWC $57,458.92 $ $ $0.00

10%

Totals
Final Estimate:

$632,048.16

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00