Lefler Residence

Client Name: Beau Lefler

Start Date: January 27, 2025
Project Sqft Total: 3889


Project Description:

Garage 700
Main 3,089
Upper 800

Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Summit County $20,000.00 $ $ $0.00

This is just an estimated budget number (Summit County permits, SWAPP control, and Surveyor cost)

Excavation and Backfill Tycon $115,186.00 $ $ $0.00

Septic System $52,630.00 (included in estimate)
Look at estimate for all budgets and what is included…

Footing and Foundation C&S Concrete $70,595.00 $ $ $0.00

A NEW BID CAME IN AFTER WE TALKED FROM SOMEONE I HAVE USED IN THE PAST. ESTIMATED COST HAS BEEN UPDATED

Foundation Weather Proofing Rocky Mountain Waterproofing $8,380.00 $ $ $0.00

This estimate covers all Waterproofing walls and Under slab Vapor barrier needed for code..

Additional Rebar NWC $0.00 $ $ $0.00

Budget number only if needed.. CONCRETE COMPANY SAID THAT WE DON’T NEED A BUDGET FOR ADDITIONAL REBAR, THIS IS ALL INCLUDED.. ESTIMATED COST HAS BEEN UPDATED

Foundation Plastering FYN Cuellars $2,000.00 $ $ $0.00

NOT Required.. This is a budget number if Owner wants it on the finish of the project..

Fill / Gravel NWC $5,000.00 $ $ $0.00

Budget number only if needed..

Steel Beams $0.00 $ $ $0.00
Steel Connections NWC $2,500.00 $ $ $0.00

Budget number only..

Material Handling NWC $5,000.00 $ $ $0.00

Budget for equipment that may be needed to move and place material around the project during construction..

Lumber Rough Sunpro $58,387.16 $ $ $0.00

This Budget number is based on a take off from my lumber supplier.. From the set of Plans provided to NWC..

Trusses Sunpro $30,530.50 $ $ $0.00

This Budget number is based on a take off from my lumber supplier.. From the set of Plans provided to NWC..

Carpentry Rough JRC Custom Homes $60,264.96 $ $ $0.00

This estimate does not include drop ceilings, siding blocking or snow removal.. This budget number would be $5,000.00 on top of the Carpentry Rough Number if needed..

Windows / Glass Doors Sierra Pacific $53,798.00 $ $ $0.00

$44,298.00 plus labor $9,500.00

Exterior Siding Material Innovative Construction $50,929.00 $ $ $0.00

Estimate includes Labor, Material and Painting (Board and Batten style) $35,029.00 Plus 1200 Sq Ft of wood side on front and back porches..@ $6100.00 WOOD SIDING HAS BEEN REMOVED FROM ESTIMATE..ESTIMATED COST HAS BEEN UPDATED
NOTE: To include a Rigid Foam Board on the exterior before installing the siding the cost will be $12,285.00 as plans show.. Please note to discuss this with owners of options included in insulation bid..

Soffit / Fascia North West Roofing $10,935.00 $ $ $0.00

Aluminum soffit and fascia

Siding Labor Innovative Construction $0.00 $ $ $0.00

Included in siding bid..

Plumbing MVPH $50,800.40 $ $ $0.00

This estimate includes all material and labor to rough in and finish the plumbing as per plans.. This estimate also has a price for a whole house hot water recirculating system, water softening system and a finish budget (Black in color, mid grade finish) for the faucets along with budgets for the tubs and toilets..

Plumbing Fixtures MVPH $0.00 $ $ $0.00

Budget included in plumbing estimate..

Electrical / Home Automation Junction Electric $33,777.75 $ $ $0.00

Please look at estimate to see additional options available..

Electrical Fixtures Junction Electric $5,000.00 $ $ $0.00

Budget number only..

Electronics Mtn top $10,000.00 $ $ $0.00

Budget for pre-wiring..

Heating HVAC Paul’s Heating $44,500.00 $ $ $0.00

Estimate includes 10 gas lines stub outs @ $700 ea $7,000.00, Range hood $675.00, make up air $725.00, Manual J&B $2,000.00, Main house system through the attic, and Apartment system under slab $28,600.00 Total $39,000.00
UNIT HEATER WAS ADDED IN THE GARAGE-$5500.00 ESTIMATED COST HAS BEEN UPDATED

Radiant Heat MVPH $66,000.00 $ $ $0.00

Main level system $66,000.00 UPPER LOFT AND GARAGE HAS BEEN REMOVED FROM THIS ESTIMATE..ESTIMATED COST HAS BEEN UPDATED
Upper loft area $11,670.00
Garage $15,400.00

Fire Sprinklers Fire services $0.00 $ $ $0.00

Not sure if we are going to need this or not.. When we are permitting the job the fire marshal will determine this at that time..

Roofing L & M North West Roofing $28,890.00 $ $ $0.00

Labor and Material for Asphalt shingles

Fireplaces Alpine Fireplace $10,346.55 $ $ $0.00

Budget from Alpine Fireplace..

Fireplace Feature Wall NWC $7,500.00 $ $ $0.00

This is just a budget, not knowing what the owner will want..

Gutter North West Roofing $7,470.00 $ $ $0.00
Heat Tape Summit Electric $0.00 $ $ $0.00

Not needed, but is high suggested to prevent any roof leaks or winter damage..

Insulation Hansen $48,383.00 $ $ $0.00

This estimate includes attic foam 4″ closed cell + 10″ open cell and gable ends foam 3″ closed cell foam Under slab 2″ closed cell foam barrier for vapor and radon $6,225.00
Optional Upgrades – exterior walls foam 2′ closed cell foam $3,675.00
NOTE: THIS IS SOMETHING WE NEED TO DISCUSS

Drywall Torres Drywall $36,900.00 $ $ $0.00
Painting Interior MC Baldwin Painting $49,079.00 $ $ $0.00

Interior main upper and lower $42,779.00
Garage interior $2,100.00
Epoxy floor in garage $4,200.00

Painting Exterior Innovation Construction $0.00 $ $ $0.00

Included in siding bid..

Lumber Finish Sunpro $12,000.00 $ $ $0.00

Paint grade budget number.. Budget does not include window wrap..

Carpentry Finish BuildworX $32,419.25 $ $ $0.00

Interior and garage
Includes Pocket Doors install labor only – BuildworX – $5,250.00 (Per Drywall)

Closets / Shelving / Built-ins BuildworX $10,000.00 $ $ $0.00

Budget for built in paint grade shelving for closets..
Labor $5,525.00
Material $4,475.00

Doors Exterior / Interior NWC $36,223.14 $ $ $0.00

Interior door budget – $15,350.31, Pocket door HD tracking system (7) $8400.00 and exterior door budget $12,472.83
High Country Iron Door – Metal Front door included

Garage Door 5 Star Building $13,195.00 $ $ $0.00

5 star building $11,945.00
North West Roofing garage door wrap $1,250.00

Railings NWC $500.00 $ $ $0.00

Interior grab rail for the stairs- $500.00

Stairs NWC $650.00 $ $ $0.00

Stair Skirting labor only – BuildworX – $650.00

Wood Ceilings / Wood Walls / Wood Columns / Etc… NWC $0.00 $ $ $0.00

No design yet..
Discuss this with the owners..

Hardware Sunpro $4,310.00 $ $ $0.00

Budget only..

Hardware Labor BuildworX $4,800.00 $ $ $0.00

Budget only..

Cabinets A&A Cabinets $74,100.00 $ $ $0.00

Area’s that are included with this budget number- Kitchen, Laundry, Pantry, Living room, Primary bath, Mudroom, Bath 1, Bath 2, Bath3, and Living/Kitchen area, and 2nd Laundry..

Countertops MaCorp $20,610.00 $ $ $0.00

Budget number only..

Mirrors / Bath Enclosures NWC $5,600.00 $ $ $0.00

Budget number only..

Tile Tubs / Showers MaCorp $58,573.10 $ $ $0.00

Material (Material handling, Setting, prepping material and grouting) and labor for all tile work throughout the House.. $48,044.10 Budget for the tile in these area’s..$10,529.00
AREA INCLUDED: Master bathroom, Bath 1, Bath 2, Bath 3, Laundry, Mudroom, and Kitchen backsplash

Floors Tile / Stone MaCorp $0.00 $ $ $0.00

Included in Tile Tubs / Showers budget..

Floors Wood MaCorp $30,053.00 $ $ $0.00

Labor and Material to install wood floors..
Labor $13,592.00
Floor material Budget $16,461.00

Deck System NWC $0.00 $ $ $0.00

Labor to install decking-$9875.00 THIS HAS BEEN REMOVED FROM THE ESTIMATE.. WE CHANGED IT TO CONCRETE PAD’S.. ESTIMATED COST HAS BEEN UPDATED
Material for deck-$12,455.91
Deck railing-$1503.23

Floors Carpet MaCorp $5,000.00 $ $ $0.00

Budget is based on 100 Yards @ $50.00 a yard..

Appliances / Built-in Vacuum Owner $25,000.00 $ $ $0.00

Budget number only.. No specs on plans to bid..

Appliance Installation NWC $2,500.00 $ $ $0.00

Budget number only..

Flatwork Prep Tycon $6,500.00 $ $ $0.00

Budget number if needed over the budget that in in the excavation budget..

Flatwork Exterior Material FYN Cuellars $105,734.50 $ $ $0.00

Labor and material for interior living floor area, garage floor, driveway (1650 sq ft), Porch cap, concrete steps, sidewalk for main entry, square path (4′ x 4′) and path by carport.. ADDED TO THIS BID -THE FLAT WORK FOR THE BACK PATTIO’S INSTEAD OF A DECK SYSTEM IN BOTH AREA’S-$9800.00 – ESTIMATED COST HAS BEEN UPDATED

Flatwork Exterior Labor FYN Cuellars $0.00 $ $ $0.00

Included in the Flatwork exterior material budget..

Driveway FYN Cuellars $0.00 $ $ $0.00

Included in flatwork exterior material budget..

Final / Pre-Landscaping Grading NWC $0.00 $ $ $0.00

Final construction grading for final inspection is included in the excavation bid..

Winter Costs NWC $5,000.00 $ $ $0.00

Budget number only..

Landscaping NWC $0.00 $ $ $0.00

Not needed for final..

Site Control / Clean-up NWC $5,000.00 $ $ $0.00

Budget to keep the job site cleaned up for all work to be done on time and on schedule..

Final Clean Clean Tex $6,500.00 $ $ $0.00

Cleaning of all duct work and final clean before move in…

Dumpster Honey Bucket $2,500.00 $ $ $0.00

Budget number..

Chemical Toilet Honey Bucket $2,500.00 $ $ $0.00

Budget number..

General Labor NWC $10,000.00 $ $ $0.00

Budget for labor work that may come up throughout the build that is not included..

Monthly Management Fee NWC $39,000.00 $ $ $0.00

Estimated 16 months… THIS HAS BEEN CHANGED TO 13 MONTHS.. ESTIMATED COST HAS BEEN UPDATED

Liability Insurance NWC $0.00 $ $ $0.00

Owner will provide own course of construction insurance

Overhead / General Expenses NWC $14,104.20 $ $ $0.00

1% OGE Fees.. ESTIMATED COST HAS BEEN UPDATED

General Contractor Fee NWC $169,250.44 $ $ $0.00

12% GC Fees.. ESTIMATED COST HAS BEEN UPDATED

Totals
Final Estimate:

$1,593,774.95

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00