NWC Barndominium

Client Name: No Worries Construction

Start Date: March 1, 2025
Project Sqft Total: 4785


Project Description:

Living Down 1495
Living Upper 1153
Total Living 2648

Garage 2137

Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Summit County $6,000.00 $ $ $0.00

After permit, we’ll need the SWAPP and surveying..

Excavation and Backfill Tycon $48,530.00 $ $ $0.00

Check estimate for the budgets per line items.

Footing and Foundation C and S $59,935.00 $ $ $0.00
Foundation Weather Proofing Rocky Mountain Waterproofing $2,500.00 $ $ $0.00
Additional Rebar NWC $5,000.00 $ $ $0.00

Only if needed..

Foundation Plastering NWC $2,500.00 $ $ $0.00

Not required..

Fill / Gravel NWC $5,000.00 $ $ $0.00

Most likely will be needed.. Most likely for the driveway..

Steel Connections NWC $1,500.00 $ $ $0.00

Budget number if needed..

Material Handling NWC $5,000.00 $ $ $0.00

For use of cranes, fork lifts , etc..

Lumber Rough Sunpro $71,064.44 $ $ $0.00

This has no contingency.. Budget number from SunPro..

Trusses Sunpro $19,748.75 $ $ $0.00

Budget number..

Carpentry Rough JRC Custom Homes $63,805.20 $ $ $0.00

There may be an additional cost for the timber work needed for front and back porch..

Windows / Glass Doors Sierra Pacific $29,542.00 $ $ $0.00

Black on Black sliders..

Exterior Siding Material Innovative Construction $42,957.50 $ $ $0.00

Innovative Construction includes Labor and material..

Soffit / Fascia North West $17,052.00 $ $ $0.00
Plumbing MVPH $42,587.50 $ $ $0.00

This budget includes a budget for soft water system- $3,000.00, Hot water Recirc system- $3,000.00 and budget for Plumbing fixtures..

Plumbing Fixtures NWC $0.00 $ $ $0.00

Look at Plumbing line item for what is included..

Electrical / Home Automation Junction $40,000.00 $ $ $0.00

Budget number only..

Electrical Fixtures NWC $7,500.00 $ $ $0.00

Owner will provide.. Budget number only..

Heating HVAC Air Design Heating & A/C $22,461.00 $ $ $0.00

This estimate includes two furnace system, AC units for both systems. May need to add for additional gas lines, Make up air and venting the hood..
Unit Heater for garage is not included

Fire Sprinklers NWC $0.00 $ $ $0.00

Not sure if this is needed for this project or not..

Roofing L & M North West $26,890.00 $ $ $0.00

This is for a shingle roof budget number..

Fireplaces Alpine Fireplace $9,744.00 $ $ $0.00

Gas fireplace budget..

Fireplace Feature Wall FYN Cuellars $34,297.00 $ $ $0.00
Gutter North West $5,710.00 $ $ $0.00
Heat Tape NWC $0.00 $ $ $0.00

Not needed but highly suggested..

Insulation Hansen Insulation $16,989.00 $ $ $0.00

Budget number as per code it may chance for upgrades..

Drywall Torres Drywall $36,000.00 $ $ $0.00
Painting Interior MaCorp $48,416.00 $ $ $0.00

Main and Upper Levels $29,183
Garage $6,411
Garage Epoxy $12,822

Painting Exterior Innovative Construction $18,832.00 $ $ $0.00

Does not include any timber staining

Lumber Finish Sunpro $11,502.96 $ $ $0.00

Budget is for paint grade material..

Carpentry Finish BuildworX $18,964.00 $ $ $0.00

Interior Trim, Barn Doors, Stairs

Closets / Shelving / Built-ins BuildworX $4,875.00 $ $ $0.00

BuildworX – Closet labor $4,875.00 Material is included in Finish material package..

Doors Exterior / Interior Frontier Woodworks $14,814.56 $ $ $0.00

High Country Iron Doors ( custom steel entry door) included in this budget..

Garage Door 5 Star $14,715.00 $ $ $0.00

5 Star Building $12,245.00 + $520 for 10×8 w/windows + $460.00 for 12×14 w/windows (not included in estimate)
North West Door Wrap $1,950.00

Railings NWC $6,000.00 $ $ $0.00

Budget number for the cinch handrail package.. Labor and Material

Stairs NWC $1,500.00 $ $ $0.00

Grab rail budget Labor and Material..

Hardware Sunpro $4,310.00 $ $ $0.00
Hardware Labor BuildworX $2,250.00 $ $ $0.00
Cabinets A&A Cabinets $48,650.00 $ $ $0.00

Custom cabinet shop..

Countertops MaCorp $16,860.00 $ $ $0.00
Mirrors / Bath Enclosures NWC $3,000.00 $ $ $0.00

Budget number only..

Tile Tubs / Showers MaCorp $35,997.97 $ $ $0.00

Walls, floors, backsplash. Labor and material.. This Number also has the tile budget included..

Floors Wood MaCorp $26,887.00 $ $ $0.00
Floors Carpet NWC $5,500.00 $ $ $0.00

Budget for 110 Yard @ $50.00 a yard..

Appliances / Built-in Vacuum Owner $15,000.00 $ $ $0.00

Budget number only..

Appliance Installation Owner $2,500.00 $ $ $0.00
Flatwork Exterior Material FYN Cuellars $48,248.00 $ $ $0.00

Concrete- Garage Floor and patios. Labor and material..

Driveway NWC $0.00 $ $ $0.00

We need to decide what we want here..

Winter Costs NWC $5,000.00 $ $ $0.00

Only if needed..

Site Control / Clean-up Owner $5,000.00 $ $ $0.00

Budget number..

Final Clean NWC $7,500.00 $ $ $0.00

This is a budget number for final window cleaning, duct cleaning and house cleaning..

Dumpster NWC $3,500.00 $ $ $0.00

Budget number only..

Chemical Toilet NWC $2,500.00 $ $ $0.00

Budget number only..

General Labor NWC $7,500.00 $ $ $0.00

Budget number only..

Hazard Insurance NWC $0.00 $ $ $0.00

Owner to provide..

Liability Insurance NWC $0.00 $ $ $0.00

Owner to provide..

Overhead / General Expenses NWC $10,021.36 $ $ $0.00

1% of construction cost..

General Contractor Fee NWC $120,021.36 $ $ $0.00

12% GC Fee’s on the cost of the project..

Totals
Final Estimate:

$1,132,178.60

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00