Bermudez Addition

Client Name: Peter and Maria Bermudez

Start Date: June 1, 2025
Project Sqft Total: 2050


Project Description:

2050 Living sq ft

Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Summit County $10,000.00 $ $ $0.00

Budget for Permits and surveying needed for this project..

Excavation and Backfill Tycon $0.00 $ $ $0.00

N/A

Footing and Foundation FYN $0.00 $ $ $0.00

N/A

Foundation Weather Proofing NWC $0.00 $ $ $0.00

N/A

Additional Rebar NWC $0.00 $ $ $0.00

N/A

Steel Connections J&J Fabrication $1,500.00 $ $ $0.00

Budget if needed..

Material Handling NWC $2,500.00 $ $ $0.00

Budget for equipment if needed to move or lift material for project..

Lumber Rough Sunpro $29,632.10 $ $ $0.00

Estimate budget from plans..

Trusses Sunpro $9,607.50 $ $ $0.00

Estimate budget from plans..

Carpentry Rough JRC Custom Homes $23,751.00 $ $ $0.00

Does not include work around eyebrow roof $75.00 per man hour

Windows / Glass Doors Sierra Pacific $11,760.00 $ $ $0.00

Estimate from plans..

Exterior Siding Material Innovative Construction $60,143.70 $ $ $0.00

WE NEED TO TALK ABOUT THIS BUDGET..

This Estimate is for the whole house..
Innovative Const Hardy Board $51,593.70
Innovative Const Insulation $8,550.00

Masonry FYN $20,717.00 $ $ $0.00

This Budget may change depending on exactly what sq ft is installed..

Soffit / Fascia North West Roofing $4,631.00 $ $ $0.00

THIS ESTIMATE IS JUST FOR THE ADDITION PART OF THE HOUSE. WE’LL NEED TO PRICE IF WE WANT TO DO THE WHOLE HOUSE TO MATCH..

Siding Labor Innovative Construction $23,468.75 $ $ $0.00

This is an Estimate for the whole house.

Plumbing MVPH $19,019.24 $ $ $0.00

Check estimate to see what is included..

Plumbing Fixtures MVPH $0.00 $ $ $0.00

included..

Electrical / Home Automation Junction electric $13,758.65 $ $ $0.00

Electrical Budget..

Electrical Fixtures Junction Electric $2,500.00 $ $ $0.00

Budget only..

Electronics Junction Electric $0.00 $ $ $0.00

We need to discuss if we want any Home Automation included in the budget..

Heating HVAC Paul’s Heating and A/C $16,725.00 $ $ $0.00

Check estimate to see what is included in budget..

Fire Sprinklers Fire Systems $0.00 $ $ $0.00

If required by county

Roofing L & M North West Roofing $6,980.00 $ $ $0.00

The estimated cost is for asphalt shingles. Optional metal roof cost will be$16,100.00

Gutter North West Roofing $2,759.00 $ $ $0.00

This estimate is for gutter on an asphalt shingle roof. If roof is metal, the cost will be $5,340.00

Heat Tape Summit Electric $0.00 $ $ $0.00

NOT REQUIRED FOR CODE BUT IS ALWAYS HIGHLY SUGGESTED..

Insulation Hansen Insulation $15,544.00 $ $ $0.00

Check estimate to see what is included..

Drywall Torres Drywall $11,400.00 $ $ $0.00
Painting Interior MC Baldwin Painting $19,183.50 $ $ $0.00

$10.50 per sq ft, includes all labor and material 1827 sq ft

Painting Exterior Innovative Construction $15,958.75 $ $ $0.00

This is an estimate for the whole house..

Lumber Finish Sunpro $7,954.19 $ $ $0.00

Budget for paint grade material..

Carpentry Finish BuildworX $7,472.00 $ $ $0.00

Does not include handrail, railing or stair components. Does not include hanging of exterior doors

Closets / Shelving / Built-ins BuildworX $2,500.00 $ $ $0.00

Master closet allowance $2,500.00

Doors Exterior / Interior Frontier Doors $3,505.58 $ $ $0.00

Frontier Doors $3,505.58
ADD FOR STEEL EXTERIOR DOOR $3,795.00

Railings BuildworX $1,000.00 $ $ $0.00

Budget number only..

Hardware Sunpro $1,500.00 $ $ $0.00

Budget number only..

Hardware Labor BuildworX $1,000.00 $ $ $0.00

Budget number only..

Cabinets A&A Cabinet $5,400.00 $ $ $0.00
Countertops MaCorp $2,098.40 $ $ $0.00
Mirrors / Bath Enclosures Beehive Glass $2,500.00 $ $ $0.00

Budget number only..

Tile Tubs / Showers MaCorp $16,741.57 $ $ $0.00
Floors Wood MaCorp $11,812.50 $ $ $0.00
Demo work and tying into the existing house. JRC $0.00 $ $ $0.00

This will be billed at labor and material..

Leveling garage concrete floor for new living area FYC $0.00 $ $ $0.00

This will be billed at labor and material if needed..

Deck replacement JRC $0.00 $ $ $0.00

This will be billed at labor and material depending on how much has to be replaced.. ( For rock work and siding )

$ $ $ $0.00
Floors Carpet MaCorp $5,801.00 $ $ $0.00
Winter Costs NWC $0.00 $ $ $0.00

Only if needed..

Site Control / Clean-up NWC $5,000.00 $ $ $0.00

Budget number..

Final Clean NWC $5,000.00 $ $ $0.00

Budget number..

Dumpster Honey Bucket $5,000.00 $ $ $0.00

Budget number..

Chemical Toilet Honey Bucket $3,000.00 $ $ $0.00

Budget number..

General Labor NWC $0.00 $ $ $0.00
Hazard Insurance NWC $0.00 $ $ $0.00

Owner to provide own insurance

Liability Insurance NWC $0.00 $ $ $0.00

Owner to provide own insurance

Overhead / General Expenses NWC $4,088.24 $ $ $0.00

1 % above cost

General Contractor Fee NWC $49,058.93 $ $ $0.00

12 % above cost

Totals
Final Estimate:

$461,971.60

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00