Hunsaker Cabin

Client Name: Russ and Rose Hunsaker

Start Date: May 1, 2026
Project Sqft Total: 3933


Project Description:

Basement 2028
Main 1905

Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Summit County $0.00 $ $ $0.00
Excavation and Backfill Paul Weller $68,000.00 $ $ $0.00

Demo of cabin site  $22,500
Foundation hole dig $7,500
Backfill, compaction, French drain $10,000
Gravel $7,000
Septic / Sewer $19,500
Water line install $1,500

Footing and Foundation C&S Concrete $80,180.00 $ $ $0.00

C&S Concrete $80,180.00
FYN Cuellars $88,380.00

Foundation Weather Proofing Rocky Mountain Waterproofing $5,790.00 $ $ $0.00
Additional Rebar $0.00 $ $ $0.00
Fill / Gravel $0.00 $ $ $0.00
Steel Beams $0.00 $ $ $0.00
Steel Connections $0.00 $ $ $0.00
Material Handling $0.00 $ $ $0.00
Lumber Rough Sunpro $76,626.94 $ $ $0.00
Trusses Wasatch Truss $23,400.00 $ $ $0.00

Wasatch Truss $23,400
Sunpro $25,650.00

Carpentry Rough Jrc Custom Homes $91,755.00 $ $ $0.00
Windows / Glass Doors Sierra Pacific $73,330.00 $ $ $0.00
Exterior Siding Material Innovative Construction $39,776.40 $ $ $0.00
Masonry FYN Cuellars $78,278.00 $ $ $0.00
Soffit / Fascia North West Roofing $0.00 $ $ $0.00
Siding Labor $0.00 $ $ $0.00

Included in exterior siding material

Plumbing MVPH $43,888.78 $ $ $0.00
Plumbing Fixtures $0.00 $ $ $0.00

Included in Plumbing

Electrical / Home Automation Junction Electric $0.00 $ $ $0.00
Electrical Fixtures $0.00 $ $ $0.00
Heating HVAC Paul’s Heating $37,975.00 $ $ $0.00
Fire Sprinklers Fire Services $19,900.00 $ $ $0.00
Roofing L & M North West Roofing $0.00 $ $ $0.00
Fireplaces Alpine Fireplace $21,890.70 $ $ $0.00
Fireplace Feature Wall $0.00 $ $ $0.00
Chimney Cap $0.00 $ $ $0.00
Gutter North West Roofing $0.00 $ $ $0.00
Heat Tape $0.00 $ $ $0.00
Insulation Hansen Insulation $26,321.00 $ $ $0.00
Drywall Torres Drywall $34,000.00 $ $ $0.00
Painting Interior Old Pine Painting $53,462.00 $ $ $0.00
Painting Exterior Innovative Const $0.00 $ $ $0.00

Included in Siding Estimate

Lumber Finish Sunpro $34,236.86 $ $ $0.00
Carpentry Finish Buildworx $22,890.75 $ $ $0.00
Closets / Shelving / Built-ins Buildworx $4,250.00 $ $ $0.00
Garage Door $0.00 $ $ $0.00

N/A

Railings Various $7,868.91 $ $ $0.00

Sunpro $4,588.91
Buildworx $3280.00

Stairs $0.00 $ $ $0.00
Wood Ceilings / Wood Walls / Wood Columns / Etc… $0.00 $ $ $0.00
Hardware $0.00 $ $ $0.00
Hardware Labor Buildworx $2,725.00 $ $ $0.00
Cabinets A&A Cabinets $29,450.00 $ $ $0.00
Countertops MaCorp $16,100.00 $ $ $0.00
Mirrors / Bath Enclosures $0.00 $ $ $0.00
Tile Tubs / Showers MaCorp $36,045.49 $ $ $0.00
Floors Wood MaCorp $25,650.00 $ $ $0.00
Decking Various $31,006.73 $ $ $0.00

Sunpro $17,439.23
Buildworx installation $13,567.50

Floors Carpet MaCorp $15,156.00 $ $ $0.00
Appliances / Built-in Vacuum $0.00 $ $ $0.00
Appliance Installation $0.00 $ $ $0.00
Flatwork Exterior Material FYN Cuellars $49,156.00 $ $ $0.00
Flatwork Exterior Labor $0.00 $ $ $0.00

Included in Flatwork material

Driveway $0.00 $ $ $0.00
Final / Pre-Landscaping Grading $0.00 $ $ $0.00
Winter Costs $0.00 $ $ $0.00
Site Control / Clean-up NWC $0.00 $ $ $0.00
Final Clean NWC $0.00 $ $ $0.00
Dumpster $0.00 $ $ $0.00
Chemical Toilet $0.00 $ $ $0.00
General Labor $0.00 $ $ $0.00
General Contractor Fee NWC $0.00 $ $ $0.00
Totals
Final Estimate:

$1,049,109.56

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00