Garcia Residence

Client Name: John and Callie Garcia

Start Date:
Project Sqft Total: 8554


Project Description:

Main 2312
Upper 2464
Basement 2553
TOTAL LIVING 7,329
Storage 576
Future Theatre 649
Garage 718
RV Garage 800
***DEDUCT $259,410.82 IF BASEMENT IS UNFINISHED***

Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Oakley City $3,250.00 $ $ $0.00

Oakley Building Permit Fee $?
Application fee $50.00
Impact fees (water & sewer $5,000 each) $10,000.00
Water Connection Fee $1,000.00
Sewer Connection Fee $750.00
Surveyor Fee $3250.00

Excavation and Backfill Tycon $73,317.00 $ $ $0.00

Includes $20,000 budget for septic system
This price may vary depending on the per landscape grade that may be required to final project.

Footing and Foundation C&S Concrete $149,925.00 $ $ $0.00 FYN $180,600
Foundation Weather Proofing Rocky Mtn Waterproofing $19,466.50 $ $ $0.00

Please see estimate for options.. Under slab insulation..$9,886.50

Additional Rebar NWC $5,000.00 $ $ $0.00

May be needed to complete the project.

Foundation Plastering FYN $3,500.00 $ $ $0.00

Not required but it does finish off the foundation.

Fill / Gravel NWC $5,000.00 $ $ $0.00

May need to complete the project.

Steel Beams J&J Fabrication $6,665.75 $ $ $0.00

Structural steel

Steel Connections J&J Fabricatior $3,500.00 $ $ $0.00

Budget number Only..

Material Handling NWC $5,000.00 $ $ $0.00

On site equipment.

Lumber Rough Sunpro $143,486.00 $ $ $0.00

Basement $20,424.00
No Framing for the Storage space and the theater

Trusses Wasatch Truss $17,649.99 $ $ $0.00 Sunpro $31,640.00
Carpentry Rough JRC Custom Homes $175,956.00 $ $ $0.00

Check estimate for what may be an additional cost.

Windows / Glass Doors Sierra Pacific $105,295.00 $ $ $0.00

Includes installation

Exterior Siding Material Innovative Construction $96,975.00 $ $ $0.00

Includes Labor, Material and paint

Masonry Fyn Cuellars $34,645.00 $ $ $0.00

Stone Columns

Soffit / Fascia North West Roofing $16,938.00 $ $ $0.00
Siding Labor Innovative Construction $0.00 $ $ $0.00

Included in Exterior Siding Material

Plumbing MVPH $85,470.00 $ $ $0.00

Budget for Plumbing Fixtures are included In this Estimate. This Budget may change depending on what is actually designed and installed..

Electrical / Home Automation Junction Electric $97,209.65 $ $ $0.00

Basement Budget = $18,872.35

Electrical Fixtures NWC $15,000.00 $ $ $0.00

Budget number only..

Electronics NWC $15,000.00 $ $ $0.00

Pre wire whole house..

Heating HVAC Paul’s Heating $85,345.00 $ $ $0.00

Furnace and A/C Main and Upper Level $47,540.00
Furnace and A/C basement $16,180.00
Mini Split and Panasonic ERV for theatre room Basement $7,350.00
Garage unit heaters $7,400.00
Gas Lines $5,400.00
Range Hood $1,475.00

Roofing L & M North West Roofing $45,700.00 $ $ $0.00

Asphalt $35,880.00
Metal $9,820.00

Fireplaces Alpine Fireplace $32,035.00 $ $ $0.00

Great and Master $19,541.75
Lower Rec Room $12,493.25

Fireplace Feature Wall FYN Cuellar $47,550.00 $ $ $0.00

Includes Great room, and primary bedroom with mantel and hearth $32,930.00
Basement fireplace with mantel and hearth $14,620.00

Chimney Cap North West Roofing $0.00 $ $ $0.00

Stone caps include in Masonry estimate..

Gutter North West Roofing $9,615.00 $ $ $0.00
Heat Tape Junction Electric $0.00 $ $ $0.00

Not required but highly suggested.

Insulation Hansen Insulation $28,020.00 $ $ $0.00
Drywall Torres Drywall $70,800.00 $ $ $0.00

Main and Upper Levels $45,600
Lower Level $25,200

Painting Interior Old Pine Painting $89,605.00 $ $ $0.00

Level 1 & 2 $48,840.00
Garage Paint $8,532.00
Exterior Timber Staining $8000.00
Epoxy Garage $11,376.00 = NOT INCLUDED IN ESTIMATE
Basement Paint $24,233.00

Painting Exterior Innovative Construction $0.00 $ $ $0.00

Included in siding bid..

Lumber Finish Frontier Woodworks $10,305.62 $ $ $0.00 Sunpro base / case and shelving $10,305.62 Frontier Woodworks Base and Case $6,563.59
Carpentry Finish BuildworX $53,969.25 $ $ $0.00

Main and Upper Trim $27,750.00
Garage Trim $4,185.50
Window Casing Main and Upper $5265.00
Pocket Door Labor $3000.00
Lower Level trim $13,768.75

Closets / Shelving / Built-ins BuildworX $17,750.00 $ $ $0.00

Cabinet walk in closet $13,500.00
Closet shelving bed 1,2 & 4, hall, foyer coat $3,750.00
Lower Level guest closet $500.00

Doors Exterior / Interior Frontier Woodworks $38,598.46 $ $ $0.00

Woodworks $19,766.46 Level 1 & 2 + $6,832.00 Basement level + Custom Entry Doors $8,690.58 = $35,289.04
Iron Doors $33,544.50 (includes multiple interior doors)Front Door $12,000.00

Garage Door 5 Star Building $15,817.00 $ $ $0.00

Budget Number only.. Price may change depending what design of door is ordered.

Railings J&J Fabrication $23,431.50 $ $ $0.00

Cinch railing $2,564.43 less expensive option for outside.
Fabrication Interior Railings $10,665.75 Exterior Railings $12,765.75

Wood Ceilings / Wood Walls / Wood Columns / Etc… NWC $0.00 $ $ $0.00

There is no budget for these items as of now..

Hardware Sunpro $5,000.00 $ $ $0.00

Door locks and closet rods $4,985.54 Budget number..

Hardware Labor BuildworX $7,000.00 $ $ $0.00

Budget number..

Cabinets A&A Cabinets $83,600.00 $ $ $0.00

Upper levels $76,000.00 Check estimate for what has been bid..
Lower wet bar $7,600.00

Countertops MaCorp $59,000.00 $ $ $0.00

Main $47,200.00
Lower $11,800.00

Mirrors / Bath Enclosures NWC $7,500.00 $ $ $0.00

Budget number..

Tile Tubs / Showers MaCorp $64,507.50 $ $ $0.00

Main $48,945.00
Lower $15,562.50

Floors Tile / Stone MaCorp $0.00 $ $ $0.00

Included in Tile tubs/shower line item

Floors Wood MaCorp $86,003.75 $ $ $0.00

Main $57,047.50
Lower $28,956.25

Suspended Slabs Olympus Precast $27,900.00 $ $ $0.00
Snow Retention North West Roofing $5,040.00 $ $ $0.00
Outside BBQ area $0.00 $ $ $0.00

Outside BBQ area is not included in estimate

Sauna $0.00 $ $ $0.00

Sauna room not included in estimate

Deck Sunpro $7,028.68 $ $ $0.00

Trex $3,528.68
Labor $3,500.00

Floors Carpet MaCorp $16,875.00 $ $ $0.00

Main $11,700.00
Lower $5,175.00

Appliances / Built-in Vacuum MLD $25,000.00 $ $ $0.00

Budget number..

Appliance Installation MLD $3,500.00 $ $ $0.00

Budget number..

Flatwork Exterior Material FYN Cuellar $96,778.20 $ $ $0.00

Concrete flooring. Includes labor and material for RV garage, basement floor, garage, front porch cap, side patio, driveway, walkout steps, front & back sidewalks

Driveway NWC $0.00 $ $ $0.00

Included in flatwork estimate

Final / Pre-Landscaping Grading Tycon $0.00 $ $ $0.00

Included in Excavation and Backfill estimate..

Winter Costs NWC $0.00 $ $ $0.00

Only if needed

Landscaping Altitude Landscape $0.00 $ $ $0.00

Not included in estimate..

Site Control / Clean-up NWC $15,000.00 $ $ $0.00
Final Clean Fresh n Clean $7,500.00 $ $ $0.00

Budget number..

Dumpster NWC $7,500.00 $ $ $0.00
Chemical Toilet Honey Bucket $5,000.00 $ $ $0.00
General Labor NWC $15,000.00 $ $ $0.00

Miscellaneous pick up work needed on project.

Liability Insurance $0.00 $ $ $0.00

Homeowner is required to obtain their own course of construction liability insurance

General Contractor Fee NWC $284,898.10 $ $ $0.00

GC Fee 13%
Main and Upper $255,054.38
Basement $29,843.72

Totals
Final Estimate:

$2,476,421.95

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00

Project Images
Attachments




 

 

Click Here to Print This Page