Addition

Client Name: Byron Ames

Start Date:
Project Sqft Total:


Project Description:

Mother in Law’s addition with single car garage

Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Excavation and Backfill Tycon $10,686.00 $ $ $0.00
Footing and Foundation C & S $18,000.00 $ $ $0.00
Fill / Gravel Tycon $0.00 $ $ $0.00

Included

Lumber Rough SunPro $32,765.00 $ $ $0.00

Truss budget is $6000.00

Carpentry Rough Abel Framing $12,000.00 $ $ $0.00
Windows / Glass Doors Sierra Pacific $5,400.00 $ $ $0.00
Exterior Siding Material SunPro $17,500.00 $ $ $0.00

Material=$17,500.00

Masonry FYN $3,700.00 $ $ $0.00
Soffit / Fascia Wasatch $4,500.00 $ $ $0.00
Siding Labor Wasatch $11,000.00 $ $ $0.00
Plumbing MVPH Inc. $9,000.00 $ $ $0.00
Plumbing Fixtures MVPH Inc. $0.00 $ $ $0.00

Included

Electrical / Home Automation Pauls Electric $7,000.00 $ $ $0.00
Electrical Fixtures Owners $1,500.00 $ $ $0.00

Owner provide, this is a budget only

Heating HVAC Pauls Heating $8,000.00 $ $ $0.00
Roofing L & M North West $9,178.00 $ $ $0.00
Gutter North West $2,800.00 $ $ $0.00
Insulation Premier $3,600.00 $ $ $0.00
Drywall Torres Drywall $7,000.00 $ $ $0.00
Painting Interior MC Baldwin $6,000.00 $ $ $0.00

epoxy the garage floor would be $1,890 extra

Painting Exterior MC Baldwin $2,000.00 $ $ $0.00
Lumber Finish SunPro $4,500.00 $ $ $0.00
Carpentry Finish Wasatch $4,800.00 $ $ $0.00
Closets / Shelving / Built-ins SunPro $2,500.00 $ $ $0.00
Doors Exterior / Interior SunPro $4,200.00 $ $ $0.00
Hardware SunPro $2,000.00 $ $ $0.00
Cabinets Summit Cabinets $15,035.00 $ $ $0.00

bid as per plan

Countertops McCorp $6,500.00 $ $ $0.00

Budget #

Mirrors / Bath Enclosures NWC $2,400.00 $ $ $0.00

Budget #

Tile Tubs / Showers McCorp $8,725.00 $ $ $0.00

Includes: Master Bathroom,Powder room, mudroom and Kitchen back splash

Floors Tile / Stone McCorp $0.00 $ $ $0.00
Floors Wood McCorp $5,700.00 $ $ $0.00
Appliances / Built-in Vacuum Owner Provides $6,500.00 $ $ $0.00

Budget #

Appliance Installation NWC $1,500.00 $ $ $0.00
Flatwork Exterior Material FYN $8,500.00 $ $ $0.00
Flatwork Exterior Labor FYN $0.00 $ $ $0.00

Included…

Driveway FYN $0.00 $ $ $0.00

Included

Site Control / Clean-up NWC $3,000.00 $ $ $0.00
Final Clean NWC $1,500.00 $ $ $0.00
Dumpster NWC $2,500.00 $ $ $0.00
Chemical Toilet NWC $2,000.00 $ $ $0.00
General Labor NWC $2,500.00 $ $ $0.00
General Contractor Fee NWC $28,000.00 $ $ $0.00
Totals
Final Estimate:

$283,989.00

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00

Project Images
Attachments




 

 

Click Here to Print This Page