New house in Jermey Ranch

Client Name: Steve and Susan Shluker

Start Date: April 1, 2022
Project Sqft Total:


Project Description:
Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Summit County $25,000.00 $ $ $0.00

This is a BUDGET NUMBER only.

Excavation and Backfill Tycon $136,243.50 $ $ $0.00

Review estimate to review what is include for the BUDGET NUMBER.
FLAT WORK PREP $2500.00
FINAL / PRE-LANDSCAPE GRADING $2500.00

Footing and Foundation Kip Slaugh $129,470.00 $ $ $0.00

Review bid for BUDGET NUMBER which is good for 30 Days.

Foundation Weather Proofing Wasatch Waterproofing $6,000.00 $ $ $0.00

This is a BUDGET NUMBER only.

Foundation Plastering FYN $5,000.00 $ $ $0.00

This is a BUDGET NUMBER only.

Fill / Gravel Tycon $10,000.00 $ $ $0.00

Additional Budget not included in Excavation bid.

Steel Beams NWC $7,500.00 $ $ $0.00

NO STEEL BEAMS OR POST ON BID SET OF PLANS.
RE-BAR $2500.00
STEEL CONNECTIONS $5000.00

Lumber Rough SunPro $170,000.00 $ $ $0.00

Rough lumber BUDGET NUMBER.

Trusses SunPro $72,348.78 $ $ $0.00

BUDGET NUMBER.

Carpentry Rough Able Construction $125,000.00 $ $ $0.00

Framing cost as per plan NO STEEL WORK INCLUDED.

Windows / Glass Doors Sierra Pacific $109,350.00 $ $ $0.00

Labor for install included in cost.

Exterior Siding Material SunPro $38,376.00 $ $ $0.00

BUDGET NUMBER is for T&G fine line 1 x 8 (Siding) NO PRE STAINING OF SIDING INCLUDED IN COST.

Masonry FYN $190,347.00 $ $ $0.00

BUDGET AS PER PLAN..review bid to see what’s included…

Soffit / Fascia SunPro $75,284.03 $ $ $0.00

BUDGET NUMBER soffit material 1 x 6 T&G fineline… $36815.03
BUDGET NUMBER facia material Black Aluminum… $15000.00
BUDGET NUMBER for labor… $23469.00

Siding Labor NWC $15,000.00 $ $ $0.00
Plumbing MVPH Inc. $40,400.00 $ $ $0.00

Budget Number is for labor and material to rough and finish plumbing without fixtures.. Review bid for what’s included…

Plumbing Fixtures NWC $0.00 $ $ $0.00

NO BID INCLUDED.. Owner or Designer provides.

Electrical / Home Automation Pauls Electric Service $70,212.85 $ $ $0.00

Review bid to see what’s in it for Budget Number. HOME AUTOMATION NOT INCLUDED

Electrical Fixtures NWC $0.00 $ $ $0.00

NO BID INCLUDED.. Owner or Designer provides.

Electronics Mountain Top Audio $10,000.00 $ $ $0.00

Pre-wire BUDGET ONLY…

Security System Mountain Top Audio $8,000.00 $ $ $0.00

FULL SYSTEM

Heating HVAC Paul’s Heating and MVPH $195,060.00 $ $ $0.00

Paul’s Heating for HVAC $40,000.00
MVPH Whole house and garage radiant heat $147060.00
LITE WIEGHT CONCRETE FOR RADIANT HEAT ON MAIN LEVEL SUBFLOOR $8000.00

Fire Sprinklers Fire Services Inc $0.00 $ $ $0.00

MAY NOT BE NEEDED.

Roofing L & M North West Roofing $26,050.57 $ $ $0.00

Review bid to see what’s included.

Fireplaces Alpine Supply Com. $42,059.18 $ $ $0.00

Review bid for what’s included.
CHIMNEY CAP $5000.00
FIRE FEATURE WALLS $20000.00

Gutter North West Roofing $10,460.34 $ $ $0.00

Review bid for what’s included.

Heat Tape Paul’s Electric Service $15,000.00 $ $ $0.00

BUDGET NUMBER ONLY…

Insulation Pick’s Insulation $22,434.00 $ $ $0.00

BUDGET NUMBER ONLY. NO CLOSE CELL FOAM IN WALLS OR CEILING

Drywall Torres Drywall $50,000.00 $ $ $0.00
Painting Interior MC Baldwin Painting $78,434.00 $ $ $0.00

Review bid to see what’s included..

Painting Exterior MC Baldwin Painting $15,000.00 $ $ $0.00

BUDGET NUMBER ONLY…TOUCH UP PAINTING ONLY. BUT DO RECOMMEND WHOLE HOUSE PAINTING

Lumber Finish SunPro $15,000.00 $ $ $0.00

BUDGET NUMBER ONLY…

Carpentry Finish Wasatch Group $40,116.00 $ $ $0.00

Interior finish work…NO WOOD CEILING, WALL, COLUMNS, ETC.. INCLUDED

Closets / Shelving / Built-ins NWC $7,500.00 $ $ $0.00

BUDGET NUMBER ONLY.

Doors Exterior / Interior SunPro $48,587.50 $ $ $0.00

BUDGET NUMBER ONLY.

Garage Door 5 Star products $16,200.00 $ $ $0.00

Review bid for what’s included.

Railings NWC $82,000.00 $ $ $0.00

BUDGET NUMBERS ONLY.

STAIR CASE $55000.00
EXTERIOR HANDRAIL $18000.00
INTERIOR HANDRAIL $9000.00

Hardware SunPro $7,500.00 $ $ $0.00

BUDGET NUMBER ONLY.

Cabinets Summit Cabinets $79,750.00 $ $ $0.00

Bid as per plan…

Countertops McCorp Inc. $28,000.00 $ $ $0.00

BUDGET NUMBER ONLY…

Mirrors / Bath Enclosures NWC $8,500.00 $ $ $0.00

BUDGET NUMBER ONLY…

Tile Tubs / Showers McCorp Inc. $50,458.62 $ $ $0.00

BUDGET NUMBER ONLY… WITH ALLOWANCE NUMBER INCLUDED… review bid to see what’s included

Floors Tile / Stone McCorp Inc. $0.00 $ $ $0.00

Included in tile tubs / showers…

Floors Wood Authentic wood floors $33,560.00 $ $ $0.00

BUDGET NUMBER ONLY…

OVERHEAD / GENERAL EXPENSES NWC $24,391.72 $ $ $0.00

1% FEE’s

MATERIAL HANDLING NWC $13,000.00 $ $ $0.00

FORK LIFT, CRANING, ETC…

WINE ROOM NWC $0.00 $ $ $0.00

NOT INCLUDED IN BID.

WINTER COSTS NWC $5,000.00 $ $ $0.00

BUDGET NUMBER ONLY.

HAZARD INSURANCE NWC $18,576.74 $ $ $0.00

BUDGET NUMBER ONLY.

LIABILITY INSURANCE NWC $4,878.35 $ $ $0.00

BUDGET NUMBER ONLY.

DECKING NWC $16,120.00 $ $ $0.00

BUDGET NUMBER ONLY.

$ $ $ $0.00
Floors Carpet Sub Zero $16,650.00 $ $ $0.00

222 yards @ $75.00 a yard for budget number…

Appliances / Built-in Vacuum Mtn land $50,000.00 $ $ $0.00

BUDGET NUMBER ONLY.

Appliance Installation MyTy $3,500.00 $ $ $0.00

BUDGET NUMBER ONLY.

Flatwork Exterior Material Kip Slaugh $102,600.00 $ $ $0.00

Material and labor BUDGET NUMBER ONLY…
MONO SLAB FOR GARAGE FLOOR ABOVE STORAGE… BUDGET NUMBER ONLY. $40000.00

Flatwork Exterior Labor Kip Slaugh $0.00 $ $ $0.00

Included in bid…

Driveway NWC $0.00 $ $ $0.00

NO BID YET…

Site Control / Clean-up NWC $15,000.00 $ $ $0.00
Final Clean NWC $7,500.00 $ $ $0.00
Dumpster NWC $12,000.00 $ $ $0.00
Chemical Toilet NWC $3,600.00 $ $ $0.00
General Labor NWC $25,000.00 $ $ $0.00

COVERS THINGS LIKE PICK UP CONSTRUCTION LABOR AS NEEDED, SURVEYING, PRE CONSTRUCTION PREP, ETC…

Monthly Management Fee NWC $54,000.00 $ $ $0.00

$3000.00 FOR 18 MONTHS

General Contractor Fee NWC $268,308.96 $ $ $0.00

11% GC FEE’s…

Totals
Final Estimate:

$2,755,328.14

Actual Total-to-Date:

$16,200.00

Total Amount Paid:

$0.00

Current Amount Due:

$16,200.00