Main House

Client Name: Chris and Ashley Wilson

Start Date: November 1, 2021
Project Sqft Total:


Project Description:
Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Epic and Oakley City $3,500.00 $ $ $0.00

Permit has already been paid… This is for reengineering.

Excavation and Backfill Goergi Excavation $44,000.00 $ $ $0.00

Septic System $15,000.00
Dif and back fill $18,000.00
Demo of existing house. $11,000.00

Footing and Foundation C&S concrete $63,500.00 $ $ $0.00

Price will change with new foundation additions.

Foundation Weather Proofing Rocky Mtn Waterproofing $7,800.00 $ $ $0.00

Budget number..

Additional Rebar NWC $2,000.00 $ $ $0.00

If Needed…

Foundation Plastering FYN $3,500.00 $ $ $0.00

Optional if needed…

Fill / Gravel NWC $4,500.00 $ $ $0.00

Budget Number (15 loads at $300.00)

Steel Beams NWC $0.00 $ $ $0.00

May be needed after we get new engineering plans.

Steel Connections SunPro $2,500.00 $ $ $0.00

Hardware needed for framing…

Material Handling NWC $3,500.00 $ $ $0.00

Forklifts and cranes…

Lumber Rough SunPro $98,500.00 $ $ $0.00

Budget number without contingency…

Trusses SunPro $55,000.00 $ $ $0.00

Budget number Only…

Carpentry Rough JRC Construction $51,000.00 $ $ $0.00

No window install…

Windows / Glass Doors Sierra Pacific $24,950.00 $ $ $0.00

Price includes install…

Exterior Siding Material FYN $64,553.50 $ $ $0.00

Review bid for what’s included…stucco

Masonry FYN $25,741.25 $ $ $0.00

Inside fireplace $10,083.75
Outside fireplace $15657.50

Soffit / Fascia North West Roofing $8,500.00 $ $ $0.00
Plumbing MVPH Inc. $18,900.00 $ $ $0.00

Labor and material to rough and finish plumbing. Does not include fixtures..

Plumbing Fixtures MVPH Inc. $11,530.00 $ $ $0.00

The budget number for the Fixtures $8530.00
The budget number for the master tub $3000.00

Electrical / Home Automation Pauls Electric $28,661.08 $ $ $0.00

The Electrical budget without light fixtures.. No home Automation bid in..

Electrical Fixtures NWC $3,500.00 $ $ $0.00

Budget number which owner will provide..

Electronics Mountain Top $5,500.00 $ $ $0.00

This is a prewire budget for whole house A/V.. $5500.00

Heating HVAC Paul’s Heating and AC $18,900.00 $ $ $0.00

Check Bid for Budget..

Roofing L & M North West Roofing $28,845.00 $ $ $0.00
Fireplaces Alpine Fireplace $12,000.00 $ $ $0.00

Budget number for gas fireplace inside and wood burner for the outside..

Chimney Cap J bar J Enterprises $3,500.00 $ $ $0.00

This is a budget number for the outside fire place..

Gutter North West Roofing $5,877.00 $ $ $0.00

Check bid for what’s include in budget..

Insulation Pick’s $14,551.00 $ $ $0.00

Check estimate for what’s in budget number..

Drywall Tores Drywall $25,750.00 $ $ $0.00
Painting Interior MC Baldwin Painting $27,152.00 $ $ $0.00

Look at estimate for what included in bid..

Lumber Finish SunPro $12,500.00 $ $ $0.00

Budget number only..

Carpentry Finish Wasatch $14,500.00 $ $ $0.00
Closets / Shelving / Built-ins Wasatch $7,500.00 $ $ $0.00

Budget number includes labor and Paint grade material..

Doors Exterior / Interior SunPro and Style doors $24,404.48 $ $ $0.00

2 metal doors for front and rear doors.. $13,604.48
Exterior man doors and interior doors budget number $10.800.00

Garage Door Five star Building Products $13,500.00 $ $ $0.00
Railings J and J fab. $15,000.00 $ $ $0.00

This is a budget number for custom steel handrail at $300.00 per foot.. 50′

Hardware SunPro $2,500.00 $ $ $0.00

This is a material budget number only..

Hardware Labor Wasatch $1,600.00 $ $ $0.00

Budget number for 16 man hours..

Cabinets Summit Cabinet $58,765.00 $ $ $0.00
Countertops McCorp $23,600.00 $ $ $0.00

Check Estimate for budget number..

Mirrors / Bath Enclosures NWC $5,500.00 $ $ $0.00

Budget number only..

Tile Tubs / Showers McCorp $23,993.75 $ $ $0.00

Look at estimate for budget numbers..

Floors Tile / Stone McCorp $0.00 $ $ $0.00

Included in tile budget..

Floors Wood McCorp $17,056.00 $ $ $0.00

Look at estimate for budget number..

Floors Carpet Sub Zero $6,250.00 $ $ $0.00
Appliances / Built-in Vacuum MLD $16,000.00 $ $ $0.00

Budget number only..

Appliance Installation MyTy $4,500.00 $ $ $0.00

Budget number only..

Flatwork Prep Goergi Excavation $2,500.00 $ $ $0.00

Budget number only..

Flatwork Exterior Material FYN $44,045.00 $ $ $0.00

This Is Labor and Material for all concrete slab’s… Basement floor not included..

Flatwork Exterior Labor FYN $0.00 $ $ $0.00

Included in bid..

Driveway FYN $0.00 $ $ $0.00

Included in bid..

Final / Pre-Landscaping Grading Goergi Excavation $2,500.00 $ $ $0.00

Budget number only..

Winter Costs NWC $2,500.00 $ $ $0.00

If needed..

Site Control / Clean-up NWC $5,000.00 $ $ $0.00
Final Clean NWC $2,500.00 $ $ $0.00
Dumpster NWC $5,400.00 $ $ $0.00
Chemical Toilet NWC $2,400.00 $ $ $0.00
General Labor NWC $5,000.00 $ $ $0.00
Hazard Insurance NWC $0.00 $ $ $0.00
Liability Insurance NWC $0.00 $ $ $0.00
Overhead / General Expenses NWC $9,867.25 $ $ $0.00

1% of over all project..

General Contractor Fee NWC $98,672.51 $ $ $0.00

10% of over all project..

Totals
Final Estimate:

$1,095,264.82

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00