Guest House

Client Name: Chris and Ashley Wilson

Start Date: November 1, 2021
Project Sqft Total:


Project Description:
Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Epic $0.00 $ $ $0.00

Included in Main House pricing..

Excavation and Backfill Georgi Construction $0.00 $ $ $0.00

Include in Main House pricing..

Footing and Foundation C&S $16,000.00 $ $ $0.00

This is for 4′ walls and 20″ footing.. Does not include slab on grade pricing..

Foundation Weather Proofing Wasatch Water Proofing $1,000.00 $ $ $0.00

Budget number only..

Additional Rebar NWC $1,000.00 $ $ $0.00

If needed..

Foundation Plastering FYN $850.00 $ $ $0.00

Budget number only..

Fill / Gravel Georgi Construction $0.00 $ $ $0.00

Included in Main house pricing..

Steel Connections SunPro $750.00 $ $ $0.00

Hardware for framing..

Material Handling NWC $1,500.00 $ $ $0.00

Forklift and cranes..

Lumber Rough SunPro $14,863.20 $ $ $0.00

Budget Number only..

Trusses SunPro $4,880.00 $ $ $0.00

Budget Number only..

Carpentry Rough JRC $11,000.00 $ $ $0.00
Windows / Glass Doors Sierra Pacific $12,300.00 $ $ $0.00

Install included in price..

Exterior Siding Material FYN $15,613.00 $ $ $0.00

Stucco bid for whole house..

Soffit / Fascia North West Roofing $3,396.00 $ $ $0.00
Siding Labor FYN $0.00 $ $ $0.00

Included in Bid..

Plumbing MVPH $6,000.00 $ $ $0.00

Rough and Finish Plumbing..

Plumbing Fixtures MVPH $1,500.00 $ $ $0.00

Budget number for fixture finish..

Electrical / Home Automation Paul’s Electric Service $8,664.00 $ $ $0.00

Look at Estimate to see what’s included..

Electrical Fixtures Owner $1,200.00 $ $ $0.00

Budget number only..

Electronics Mountain top.. $1,200.00 $ $ $0.00

Budget number Only..

Heating HVAC Paul’s Heating $4,500.00 $ $ $0.00
Roofing L & M North West Roofing $4,703.00 $ $ $0.00
Gutter North West Roofing $1,496.00 $ $ $0.00
Insulation Pick’s $2,387.00 $ $ $0.00
Drywall Torres Drywall $4,650.00 $ $ $0.00
Painting Interior MC Baldwin $5,000.00 $ $ $0.00
Lumber Finish SunPro $1,600.00 $ $ $0.00

Budget Number Only..

Carpentry Finish Wasatch $4,200.00 $ $ $0.00

Budget Number Only..

Closets / Shelving / Built-ins Wasatch $2,500.00 $ $ $0.00

Budget Number Only..

Doors Exterior / Interior SunPro $2,500.00 $ $ $0.00

Budget Number Only..

Railings J and J Fab.. $12,000.00 $ $ $0.00

Budget Number for 40′ at $300.00 per foot

Hardware SunPro $1,000.00 $ $ $0.00

Budget Number only..

Hardware Labor Wasatch $1,250.00 $ $ $0.00
Cabinets Summit Cabinet $12,300.00 $ $ $0.00
Countertops McCorp $2,500.00 $ $ $0.00

Budget Number Only..

Mirrors / Bath Enclosures NWC $800.00 $ $ $0.00
Tile Tubs / Showers McCorp $4,100.00 $ $ $0.00
Floors Tile / Stone McCorp $0.00 $ $ $0.00

Included in price..

Floors Wood McCorp $5,214.40 $ $ $0.00
Floors Carpet Sub Zero $1,000.00 $ $ $0.00
Appliances / Built-in Vacuum Owner $10,000.00 $ $ $0.00

Budget Number Only..

Appliance Installation MyTy $1,500.00 $ $ $0.00

Budget Number Only..

Flatwork Prep Georgi Construction $1,200.00 $ $ $0.00
Flatwork Exterior Material FYN $2,500.00 $ $ $0.00

Budget for Labor and Material to pour front porch and back porch..

Final / Pre-Landscaping Grading Georgi Construction $0.00 $ $ $0.00

Include in Main house pricing..

Winter Costs NWC $1,500.00 $ $ $0.00

If Needed..

Site Control / Clean-up NWC $2,000.00 $ $ $0.00
Final Clean NWC $2,500.00 $ $ $0.00
Dumpster NWC $0.00 $ $ $0.00

Include in Main house pricing..

Chemical Toilet NWC $0.00 $ $ $0.00

Include in Main house pricing..

General Labor NWC $2,500.00 $ $ $0.00
Hazard Insurance NWC $0.00 $ $ $0.00
Liability Insurance NWC $0.00 $ $ $0.00
Overhead / General Expenses NWC $1,991.17 $ $ $0.00

1% Overhead / General Expenses

General Contractor Fee NWC $19,911.66 $ $ $0.00

10% General Contractor Fee

Totals
Final Estimate:

$221,019.43

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00