Herbert Home

Client Name: Jeff and Britta Herbert

Start Date: October 24, 2022
Project Sqft Total:


Project Description:
Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Summit County $15,000.00 $ $ $0.00

Budget Number Only…

Excavation and Backfill Tycon $54,035.00 $ $ $0.00

Look at bid to decide what is need and what is included…

Footing and Foundation FYN $117,248.00 $ $ $0.00
Foundation Weather Proofing Rocky Mountain $2,030.00 $ $ $0.00

Option 2 –$2030.00 on bid..

Additional Rebar NWC $2,500.00 $ $ $0.00

Rebar for additional concrete pads

Foundation Plastering FYN $0.00 $ $ $0.00

Optional

Fill / Gravel Tycon $2,500.00 $ $ $0.00

Budget Only …

Steel Beams NWC $0.00 $ $ $0.00

Not Needed…

Steel Connections J and J fab. $3,500.00 $ $ $0.00

Budget for brackets if needed..

Material Handling NWC $7,200.00 $ $ $0.00

Budget for 4 months of for framers to move material and setting beams as per needed.. @ $1800.00 Per month

Lumber Rough SunPro $150,610.56 $ $ $0.00

Budget number for Rough lumber

Trusses SunPro $42,900.00 $ $ $0.00

Budget number

Carpentry Rough JRC $111,775.00 $ $ $0.00

Additional cost will be add for the Post and Beam work on front and back porches.. ($65.00 per man hrs)

Windows / Glass Doors Sierra Pacific $67,125.00 $ $ $0.00

Window package $67125.00 with
Labor to install windows included…

Exterior Siding Material Innovation Construction $64,191.00 $ $ $0.00

Bid is for material and labor..$52591.00 Budget for barn wood siding.. $6500.00
ADDITION FOR WOOD AFTER TAKING ROCK OFF… ADDED 340 SQ FT $5100.00

Masonry FYN $98,464.00 $ $ $0.00

All Exterior stone as per plan plus entry door area ..
REMOVED 340 SQ FT FROM BID AND ADDED WOOD IN…

Soffit / Fascia North west roofing $25,046.00 $ $ $0.00
Siding Labor Innovation product $0.00 $ $ $0.00

Included in the Material bid..

Plumbing MVPH $30,900.00 $ $ $0.00

Check bid for what is included..

Plumbing Fixtures MVPH $10,000.00 $ $ $0.00

Budget number for fixtures, including some sinks, the master tub and faucet.

Electrical / Home Automation Pauls Electric Service $80,767.45 $ $ $0.00

Check bid for what’s included..

Electrical Fixtures Pauls Electric Service $10,000.00 $ $ $0.00
Electronics Mountain top $0.00 $ $ $0.00

owner will supply

Heating HVAC Pauls Heating and AC $38,925.00 $ $ $0.00

Bid $36100.00
Additional gas lines 4 @$500.00 ea = $2000.00
Venting of range hood $350.00
Makeup air $475.00

Roofing L & M North West Roofing $47,868.00 $ $ $0.00

Shingles Labor and Material $26,920.00
Metal Labor and Material $20,948.00

Fireplaces Alpine fireplace $19,203.70 $ $ $0.00

Budget number as per plans ADD THE MAIN LIVING ROOM FIREPLACE AS A WOOD BURNER

Fireplace Feature Wall FYN $20,000.00 $ $ $0.00

Stone for living room and master bedroom $30,132.00 Check Estimate for what’s included
Cement Hearth budget only $5000.00… THE NEW BUDGET WITH ROCK REMOVED FROM FIREPLACES IS $20000.00

Gutter North West Roofing $6,912.00 $ $ $0.00

What is bid… 380′ of gutter and 195′ of downspout

Heat Tape Pauls Electric Service $0.00 $ $ $0.00

Only if needed…

Insulation Pick’s Insulation $32,696.00 $ $ $0.00
Drywall Torres $49,000.00 $ $ $0.00
Painting Interior MC Baldwin Painting $78,256.00 $ $ $0.00

House $65568.00
Garage $3172.00
Epoxy garage floor $9516.00

Painting Exterior MC Baldwin Paint $6,500.00 $ $ $0.00

LP siding painting is include in the Siding price…
Budget number for staining of beams if needed.

Lumber Finish Frontier Woodworks $45,401.34 $ $ $0.00

Add for hand Hewn box beams $45,806.00 FAUX BEAM MATERIAL IS ADDED TO THIS BID…
Faux beams budget number $8000.00

Carpentry Finish Wasatch Group $50,907.50 $ $ $0.00

Check Estimate for what is included.. ($60907.50) Minus of $10,000.00 for labor if using the Faux Beams instead of Hewn box beams

Closets / Shelving / Built-ins Wasatch Group / SunPro $12,000.00 $ $ $0.00

Labor and Material Budget only..

Doors Exterior / Interior Styles Doors $23,890.00 $ $ $0.00

Metal exterior doors.. Interior doors are included in the finish lumber..

Garage Door Five Star $26,500.00 $ $ $0.00

4-10’x9′ garage doors…

Railings J and J fab. $8,500.00 $ $ $0.00

budget for metal stair railings..

Wood Ceilings / Wood Walls / Wood Columns / Etc… NWC $0.00 $ $ $0.00

Ceiling beam work included in finish carpentry

Hardware SunPro $4,500.00 $ $ $0.00

Budget for Hardware

Hardware Labor Wasatch Group $4,500.00 $ $ $0.00

Budget for Hardware labor

Cabinets A and A cabinets $128,475.00 $ $ $0.00

Updated price for master closet, gunroom and bedroom #1 and #2 window set design…
Budget for the bedrooms $14,600.00
Budget for master closet $9,450.00
Budget for office $9,300.00
Budget for gun room $5,050.00
Total for Budget numbers $38,400.00

Countertops MaCorp $39,500.00 $ $ $0.00

Fab and labor to install $27000.00
Material… Group 3 or 4.. 5 slab needed $12500.00

Mirrors / Bath Enclosures Bee Hive Glass $11,200.00 $ $ $0.00

Budget Number for shower glass and mirrors

Tile Tubs / Showers MaCorp $72,861.06 $ $ $0.00

Budget number for labor and material to set tile… labor $29559.0 setting material $24613.78
Budget for Higher end tile $18688.28

Floors Tile / Stone MaCorp $0.00 $ $ $0.00

Included in Tile Tubs / Showers bid…

Floors Wood MaCorp $31,825.00 $ $ $0.00

Labor to install wood floor $4.00 a sq ft (3350 Sq ft) $13400.00
Material ranges form $3.50 to $7.00 for LVP and around $11.00 for real wood… ($5.50 WAS USE FOR BUDGET NUMBER)

Radon gas System NWC $8,250.00 $ $ $0.00

Budget Number per Sq Ft price $1.50

$ $ $ $0.00
Floors Carpet Pro Source $13,000.00 $ $ $0.00

Budget at $50.00 a Yard (260 yards)

Appliances / Built-in Vacuum Mountain land $0.00 $ $ $0.00

PROVIDED BY OWNER… $48,584.26

Appliance Installation MyTy $3,033.00 $ $ $0.00
Flatwork Prep Tycon $5,000.00 $ $ $0.00

Budget number

Flatwork Exterior Material FYN $43,162.00 $ $ $0.00

Check Budget to adjust bid… Remove the back porch steps going off into the back yard -$9716.0

Flatwork Exterior Labor FYN $0.00 $ $ $0.00

Included in material budget..

Driveway FYN $12,800.00 $ $ $0.00

Budget for sidewalk and driveway 1600 sq ft

Winter Costs NWC $3,000.00 $ $ $0.00
Site Control / Clean-up NWC $10,000.00 $ $ $0.00

On site control durning building…

Final Clean NWC $5,000.00 $ $ $0.00
Dumpster NWC $6,000.00 $ $ $0.00
Chemical Toilet NWC $3,200.00 $ $ $0.00
General Labor NWC $10,000.00 $ $ $0.00
Hazard Insurance Owners $0.00 $ $ $0.00

Owner needs to Provided

Liability Insurance NWC $0.00 $ $ $0.00

1% On cost of construction,,, WE’LL COVER THIS IN THE OVERHEAD / GENERAL EXPENSES

Overhead / General Expenses NWC $17,776.58 $ $ $0.00

1% Above cost of construction

General Contractor Fee NWC $213,318.91 $ $ $0.00

12% Above cost of construction

Totals
Final Estimate:

$2,008,753.10

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00