House Remodel / Addition

Client Name: Brent and Linda Flynn

Start Date: January 1, 2023
Project Sqft Total:


Project Description:

Estimate SQ Ft of new living 4800 sq ft
Estimate SQ Ft of old living to be remodeled 3198 sq ft
Estimate SQ FT of new garage space 2400 sq ft
Estimate SQ FT of old garage space to be remodeled 722 sq ft

Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Various $7,626.68 $7,626.68 $7,626.68 $0.00

Printing of plans $977.96 Temporary power $1,988.76 Perk Tests $4,500.00 Summit County Permit $40.00 Update Plans $119.96

Excavation and Backfill Various $119,372.35 $105,327.50 $105,327.50 $0.00

Tycon foundation/footing $27,822.50, FYN Cuellar’s porch excavation $13,500.00 Tycon Repair water line Tycon $5,749.60 Backfill Tycon 10,782.00 Tycon 47,473.40

Footing and Foundation FYN Cuellars Constructrion $204,636.00 $204,636.00 $204,636.00 $0.00

Footing FYN Cuellar’s 77,830.00, Foundation FYN Cuellar’s 126,806.00

Foundation Weather Proofing Rocky Mountain Waterproofing $8,530.00 $8,530.00 $8,530.00 $0.00
Steel Beams J and J Fabrication $46,958.49 $19,287.00 $19,287.00 $0.00

This number will go up because we have added additional steel beams and brackets..

Material Handling NWC $10,800.00 $ $ $0.00
Lumber Rough Sunpro $148,687.21 $109,798.26 $109,798.26 $0.00
Trusses Sunpro $45,000.00 $36,907.85 $36,907.85 $0.00
Carpentry Rough JRC Custom Building $165,559.50 $153,387.50 $153,387.50 $0.00

Estimate did not have actual cost for the remodel part of the build… JRC Custom Homes $77,612.50 & 75,775.00

Windows / Glass Doors Sierra Pacific Windows $65,700.00 $ $ $0.00
Exterior Siding Material Innovative $44,670.00 $ $ $0.00

whole addition bid with board and batten.. No stone on exterior at this time…

Masonry Fyn $0.00 $ $ $0.00
Soffit / Fascia North west roofing $29,920.00 $ $ $0.00
Plumbing Most Valuable Plumbing $54,100.00 $2,900.00 $2,900.00 $0.00

Look at estimate to see what is actually included..

Plumbing Fixtures Ma Corp $1,125.00 $ $ $0.00

Bathroom sinks estimated from countertop company. NO OTHER PLUMBING FIXTURES INCLUDED IN PLUMBING BID

Electrical / Home Automation Pauls Electric Service $68,415.00 $ $ $0.00

Budget number only.. Need to walk house with owner and cost unknown on remodel part of house…
THE ELECTRICAL BUDGET WILL INCREASE FROM THE NUMBER DO TO REMODEL WORK.. AND WHAT IS ADDED THAT WAS NOT ON THE PLANS TO BID..

Electrical Fixtures Owner $0.00 $ $ $0.00

Provided by owner..

Electronics Mountain Top Audio $18,500.00 $ $ $0.00

Pre-wire speakers, data, and shades

Heating HVAC Paul’s Heating and A/C $40,000.00 $ $ $0.00

Budget number only… need to walk with owner to design the system…

Fire Sprinklers Fire Services $25,110.00 $ $ $0.00

Price does not include existing house…

Roofing L & M North West Roofing $67,490.00 $ $ $0.00

See estimate for what is bid… No metal roof on bid…

Fireplaces Alpine Gas Fireplace $40,000.00 $ $ $0.00

Budget number… I still don’t have Hearth and home’s number yet..

Gutter North west roofing $8,520.00 $ $ $0.00
Insulation Empire Insulation $36,621.00 $ $ $0.00
Drywall Torres Drywall $55,000.00 $ $ $0.00

Budget number still needs to walk it and measure it..

Painting Interior MC Baldwin Painting Inc, $100,800.00 $ $ $0.00

Bid Includes House $70,190.00, Garage and storage $11,277.00 and Epoxy the garage and storage floors $19,332.00

Painting Exterior Innovative $18,812.25 $ $ $0.00
Lumber Finish Sunpro $40,000.00 $ $ $0.00

Budget number..

Carpentry Finish Wasatch Group $41,899.00 $ $ $0.00
Closets / Shelving / Built-ins Wasatch Group $10,000.00 $ $ $0.00

Material and labor… Budget only…

Doors Exterior / Interior Styles Iron Door $32,940.00 $4,720.00 $4,720.00 $0.00

Budget number only… Metal doors $9,440.00, Exterior doors $6,000.00, Interior doors $17,500.00

Garage Door 5 Star Building $70,360.00 $ $ $0.00
Railings NWC $0.00 $ $ $0.00

Still need to decide on design and get bids..

Stairs NWC $0.00 $ $ $0.00

Still need to decide on design and get bids..

Wood Ceilings / Wood Walls / Wood Columns / Etc… $0.00 $ $ $0.00
Hardware SunPro $10,000.00 $ $ $0.00

Budget number..

Hardware Labor Wasatch Group $10,000.00 $ $ $0.00

Budget number..

Cabinets A and A Cabinet $106,875.00 $ $ $0.00
Countertops Ma Corp $35,550.00 $ $ $0.00
Mirrors / Bath Enclosures NWC $11,000.00 $ $ $0.00

Budget number… Bath Enclosure’s $6,000.00 Mirrors $5,000.00

Tile Tubs / Showers Ma Corp $65,396.04 $ $ $0.00

Check tile bid for what is included..

Floors Tile / Stone $0.00 $ $ $0.00
Floors Wood Ma Corp $14,300.00 $ $ $0.00
Concrete Cutting Saw Jockey $1,500.00 $1,500.00 $1,500.00 $0.00
Surveying Jason Jenkins PLS $6,100.00 $6,100.00 $6,100.00 $0.00
Demo Work Various $43,820.00 $43,820.00 $43,820.00 $0.00

FYN Cuellar’s Exterior demo $12,870.00 Ma Corp Interior demo $10,750.00 Ma Corp Exterior Deck demo $6,700.00 FYN Cuellar’s Find Existing Footing $13,500.00

$ $ $ $0.00
Floors Carpet Owner $21,000.00 $ $ $0.00

Budget number.. I’M SURE THAT THE TILE, WOOD FLOORS AND CARPET NUMBERS WILL CHANGE AFTER WHAT IS ACTUALLY INSTALLED..

Appliances / Built-in Vacuum Mountain Land Design $39,957.53 $ $ $0.00
Appliance Installation Mountain Land $5,000.00 $ $ $0.00

Budget Number…

Flatwork Prep Tycon $0.00 $ $ $0.00

Will need to be done…

Flatwork Exterior Material FYN $133,110.50 $94,110.50 $94,110.50 $0.00

Budget number for Flatwork that needs to be done for exterior to be finalized.. Labor and Material..
Concrete FYN Cuellar’s 5,870.00 & 88,240.50

Final / Pre-Landscaping Grading Tycon $0.00 $ $ $0.00

Needs to be done before final…

Winter Costs Various $13,765.00 $13,765.00 $13,765.00 $0.00

NWC 150.00 NWC 150.00 Snow removal/french drain, Tycon 7,985.00 Snow removal, Tycon $2,730.00 Thawing sewer line, Tycon $450.00 Snow removal, Tycon $2,300.00

Site Control / Clean-up Owner $0.00 $ $ $0.00

Billed if done by someone besides owner..

Final Clean Owner $0.00 $ $ $0.00

billed if done by someone besides owner..

Dumpster $3,200.00 $2,648.00 $2,648.00 $0.00

Waste recycling $316.86 Honey Bucket $1,308.90 & $1,022.24

Chemical Toilet Honey Bucket $6,000.00 $2,792.52 $2,792.52 $0.00
General Labor NWC $0.00 $ $ $0.00

added if need as the project goes on..

Monthly Management Fee NWC $72,000.00 $48,000.00 $48,000.00 $0.00

Based on 24 months at $3,000.00

Overhead / General Expenses NWC $21,450.96 $8,698.55 $8,698.55 $0.00

1 % Overhead and General Expenses

General Contractor Fee NWC $321,779.45 $130,238.51 $130,238.51 $0.00

15 % GC Fee

Totals
Final Estimate:

$2,568,956.96

Actual Total-to-Date:

$1,004,793.87

Total Amount Paid:

$1,004,793.87

Current Amount Due:

$0.00