Projects Test

yourproseo@gmail.com

Barker Residence

Client Name: Kevin Barker

Start Date: April 1, 2023
Project Sqft Total: 5419


Project Description:

Main Level Sq. Ft. 4795
Upper Level Sq. Ft. 624
Garage Sq. Ft. 1352

Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Various $6,750.55 $10,809.61 $10,809.61 $0.00 Paid = Oakley City $5308.09, $50.00 – PC Printink $622.54, $550.92, $38.82, $190.18 – Staples $49.06 – Baseline Surveying $4,000.00
Excavation and Backfill Tycon $35,945.64 $87,043.64 $87,043.64 $0.00 Paid = Tycon $2204.26 (water line materials), $16,901.38 (footing and gravel), $24,700.50 (french drain, garage) $6,515.00 roof drains $25,500.00 propane tanks $11,222.50 – Driveway & Asphalt

Tycon Septic System $16,840.00, Propane tanks $25,500.00, Roof Drains $6,515.00
Overage for driveway and asphalt – Tycon $11,222.50

Footing and Foundation FYN Cuellar $230,607.00 $230,607.00 $230,607.00 $0.00 Paid = FYN $170,000, $31,850.00, $28,757.00
Foundation Weather Proofing Rocky Mountai Waterproofing $5,580.00 $5,580.00 $5,580.00 $0.00 Rocky Mountain Waterproofing $5,580.00
Additional Rebar NWC $5,000.00 $ $ $0.00

ONLY IF NEEDED…

Fill / Gravel Tycon $10,000.00 $11,730.00 $11,730.00 $0.00 Tycon $11,730.00,

ONLY IF NEEDED… MOST LIKELY WE WILL NEED THIS FOR THE DRIVEWAY AND OUTSIDE PREP,,

Steel Beams Drut Kustom Welding and Fabrication $134,525.00 $137,285.00 $137,285.00 $0.00 Paid = Drut $43,962.50, $24,200.00, $2,760.00, $66,362.50
Steel Connections NWC $5,000.00 $531.00 $531.00 $0.00 Drut = $531.00

Connections for building that is unknown at this time..

Material Handling NWC $10,800.00 $3,136.50 $3,136.50 $0.00 Ivan’s Crane $1,336.50, JRC $1,800.00

Equipment needed to move material around job site..

Lumber Rough Sunpro $162,933.92 $232,551.98 $232,551.98 $0.00 Paid = Sunpro $32,208.23, $46,886.93, $31,794.49, $37,010.13, $23,143.20. $21,943.45, $13,767.57, $12,603.85, $4,022.00, $7,599.21, $1,558.51 CREDIT $12.34, Ace $56.75

See Sunpro Quote.. Timbers Not in this bid…

Trusses Sunpro $129,570.87 $114,937.07 $114,937.07 $0.00 Timber Trusses $101,850.87 (as of 2/2/24) $1,161.95. -$8,128.11 (credit), $3,883.60, $15,174.55 – Wasatch Timber $994.21

Budget Number.. $27,720.00 With out the Timber Truss build and install.

Carpentry Rough Jrc Custom Homes / 4G $235,756.96 $343,854.29 $343,854.29 $0.00 Paid JRC= $103,600.00, $31,800.00, $32,051.00, $13,175.00, $20,640.00, $16,285.00, $30,335.00, 23,422.00, $9,230.00, $3,510.00 4G = $11,684.96 (as of 2/2/24), $20,055.19 (3/5/24), $11,850.00, $6,416.14, $9,800.00

Look at what is included in the estimate..
STILL GETTING BUDGET ON TIMBER TRUSS BUILDING AND INSTALLING..

Windows / Glass Doors Sierra Pacific $204,112.00 $204,510.00 $204,510.00 $0.00 Sierra Pacific $165,510.00, Sierra Pacific $39,000.00

Net $165,112.00 Labor $39,000.00

Exterior Siding Material SunPro $50,557.83 $59,566.84 $59,566.84 $0.00 Sunpro $40,561.69, $13,095.98,$2,164.84 North West Roofing $3,744.33

MATERIAL BUDGET $38,839.98
New budget for new design. $46,813.50 an increase of $7,973.52
Metal corners and flashings $3,744.33

Masonry FYN $292,855.00 $292,855.00 $292,855.00 $0.00 Stone FYN – $50,000.00, $50,000.00, $75,000.00, $20,000.00, $75,235.00 – FYN Angle Iron $22,620.00

EXTERIOR $292,855.00 (savings of $37,575.00 with new bid)

Soffit / Fascia JRC/NORTH WEST $98,201.92 $75,359.01 $75,359.01 $0.00 Sunpro $26,280.80, $179.21, CREDIT -$2,200.00 North West Roofing $6,918.00, $6,918.00, $2,613.00 JRC $15,000.00, $19,650.00

Newest budget number with all wood soffit and metal fascia..
JRC labor for soffit $34,650.00
Sun Pro material for soffit $47,715.92plus tax.
North West Labor and material for metal soffit $15,836.00
Total $98,201.92

Siding Labor Innovative $42,200.00 $42,108.38 $42,108.38 $0.00 Innovative Construction $2,308.38, JRC $15,000.00, $15,000.00,$9,800.00

LABOR BUDGET $32,300.00
New budget for new design. $42,200.00 a increase of $9,900.00

Plumbing MVPH $46,450.00 $51,040.72 $51,040.72 $0.00 $1,650.00 overage for filter & shut-off valve $24,650.72, $600.00 (extra)

Bid as per plan with no finish fixtures included.. Added a whole house filter with install $850.00

Plumbing Fixtures Mountain Land Design $33,132.25 $35,501.70 $35,501.70 $0.00 Mountain Land Design $1,466.15, $16,566.13, $376.07, $16,178.22 MaCorp $915.13

BUDGET FROM DESIGNER…$31,586.03
Upper bathroom added…New budget number $33,132.25

Electrical / Home Automation PAULS ELECTRIC SERVICE $78,641.15 $146,245.95 $146,245.95 $0.00 $50,512.73, $8,759.89, $2,042.21, $17,644.69, $15,998.75 -Electrical $41,030.14, $10,257.54 lighting control

Check Estimate for what is on this bid… NOTE Price may change depending on designer specs and what is actually installed..
LIGHTING CONTROL BUDGET NUMBER FOR HOUSE THIS SIZE $70,00.00 (NOT INCLUDED IN ESTIMATED COST BID)

Electrical Fixtures NWC $28,600.00 $ $ $0.00

BUDGET FROM DESIGNER..

Electronics Mountain Top $52,409.20 $73,184.46 $73,184.46 $0.00 $7,205.00, $25,753.78, $1,335.68, $26,350.62, $2,482.96, $445.23, $8,783.54, $827.65
Security System NWC $0.00 $ $ $0.00
Heating HVAC Pauls Heating and A/C /MVPH Inc. $34,600.00 $46,100.00 $46,100.00 $0.00

A/C

Radiant Heat MVPH $121,396.00 $187,396.00 $187,396.00 $0.00 Paid = $4,128.00, $48,558.40, $16,500.00, $68,709.60, $24,750.00, $24,750.00

Notes: Snowmelt complete outdoor system is $26.00 to $30.00 per sq ft Depending on how broke up and spaced out the system is.
Snowmelt prep only is $11.00 per sq ft MVPH $66,000.00 for the Snow melt

Fire Sprinklers Fire Services Inc $24,900.00 $24,900.00 $24,900.00 $0.00 20,200, 2,600.00, $2,100.00
Roofing L & M Northwest Roofing $112,905.00 $112,905.00 $112,905.00 $0.00 North West $56,452.50, $28,226.25, $28,226.25

New bid for Metal and shingles mix. $112,905.00 (saved $16,767.00 with new estimate)

Fireplaces Alpine Fireplaces $55,645.85 $54,540.70 $54,540.70 $0.00 Alpine$9,010.70, $8,750.00, $400.00 Hearth and Home $18,190.00, $18,190.00

Alpine Fireplace $8,750.00
Hearth & Home $18,190.00

Fireplace Feature Wall FYN $82,845.00 $82,845.00 $82,845.00 $0.00 MaCorp $15,376.00, $8,534.00 Drut Kustom $14,285.00, $2,310.00, $1,955.00, FYN $38,885.00, A&A Cabinet $1,500.00

This estimate is for all interior rock work as per Sq Ft on plans..
STILL NEEDED NEW PRICING ON THE FIREPLACE WALLS AFTER NEW DESIGN SPEC’S. AS SOON AS THE FIRE PLACES ARE IN PLACE I’LL BE ABLE TO GET THEM BID OUT.

Chimney Cap Northwest Roofing $48,829.00 $48,829.00 $48,829.00 $0.00 North West Roofing $4,320.00 Drut Kustom $19,940.00, FYN $24,569.00

Price as per plans for budget.. (4)

AS SOON AS THE CHIMNEY’S ARE BUILT OUT WE WILL MEASURE FOR THE ROCK CAPS AND HAVE A BUDGET ON THAT.

Gutter Northwest Roofing $16,612.00 $16,615.00 $16,615.00 $0.00 North West Roofing $16,615.00

Gutters $16,612.00..
Snow Retention $30,855.00 This is not required but highly suggested..
Total for both $47,467.00

Heat Tape Pauls electric service $0.00 $ $ $0.00

Needed before finished but not required..

Insulation Hansen Insulations $64,865.00 $64,855.00 $64,855.00 $0.00
Drywall Torres Drywall $60,800.00 $60,800.00 $60,800.00 $0.00 Torres Drywall $50,800.00, $10,000.00
Painting Interior MC Baldwin $84,998.00 $99,984.73 $99,984.73 $0.00 Sherwin Williams Samples $74.13, Mc Baldwin exterior beams $9,000.00, Intermountain Coatings $12,918.60, MC Baldwin Interior $13,153.00, $25,000.00, $22,000.00, $4,087.00, $12,412.00,Stain Railing $1340.00

Interior $61,087
Garage $2,839
Garage Epoxy Floor $7,572
Total $71,498.00
Exterior beams $9,000.00
Interior wood ceilings and interior beams added to existing bid $4,500.00
NEW TOTAL $84,998.00

Painting Exterior SunPro $0.00 $ $ $0.00

Wood siding is bid pre stained..

Lumber Finish Sunpro $21,093.61 $20,233.82 $20,233.82 $0.00 Sunpro $127.20, Frontier Doors $4,904.10, $15,202.52

Bid is based on base and door casing (paint grade material) NO WINDOW WRAP..

Carpentry Finish Wasatch Group $83,866.75 $83,866.75 $83,866.75 $0.00 BuildworX $66,500.55, $17,366.20

Look at estimate to see what is included..

Closets / Shelving / Built-ins Wasatch Group $15,000.00 $ $ $0.00

This a budget number only.. This estimate is if the finish carpenter builds paint grade shelving
BUDGET FROM DESIGNER..APPROVED

Doors Exterior / Interior Frontier Woodworks $51,698.96 $48,750.29 $48,750.29 $0.00 Email from Kevin 11/15 requesting Single Panel Alder Doors High Country Iron Doors $7,596.50, $3,798.25,$5,748.25 Frontier Doors $21,349.90, $10.257.39

Designer/owner choice = Single panel shaker – / Alder $23,343.70
High Country Iron Doors $18,986.50
Frontier wood works front door $9,368.76

Garage Door 5 Star Building $33,570.00 $33,570.00 $33,570.00 $0.00

Budget number off plan details.. $89,800.00
STILL NEED SPEC’S FROM DESIGNER..

New budget number $33,570.00 (ordered) DESIGNER APPROVED

Railings Knox Custom Fabrication $18,350.00 $19,345.00 $19,345.00 $0.00 Drut $2,970.00, $16,375.00

Budget number..

Stairs Knox Custom Fabrication $235,605.60 $235,605.60 $235,605.60 $0.00 Paid Rocky Mtn $117,802.80, $58,900.00, $48,900.00, $10,002.80

Rocky Mountain Stairs…$235,605.60
ALL WOOD STAIRCASE ..

Wood Ceilings / Wood Walls / Wood Columns / Etc… SunPro $46,574.50 $34,628.35 $34,628.35 $0.00 Sunpro $31,069.19, $1,188.33, $635.83, MaCorp $1,735.00

Material budget $46,574.50 (THIS IS NOT PRE STAINED) Stain Is added in the painters budget number.

Hardware NWC $17,464.16 $16,525.08 $16,525.08 $0.00 Sunpro $9,464.16, $5,774.88, MLD $139.69 CREDIT -$793.65, BuildworX $1,940.00

BUDGET FROM DESIGNER.. Door hardware $5,700.00, Bath accessories $2,300.00, Pocket door Hardware $9464.16

Hardware Labor Wasatch group $5,419.00 $5,419.00 $5,419.00 $0.00 BuildworX $5,419.00

Budget number.. Price may vary depending what hardware is used..

Cabinets A & A Cabinets $115,500.00 $121,800.00 $121,800.00 $0.00 Kitchen/Pantry up $6,300 from budget to final design

This does not include any closet cabinets…
DESIGNER APPROVED BUDGET NUMBER

Countertops MaCorp $82,085.00 $82,085.00 $82,085.00 $0.00 MaCorp $38,874.60, $5,435.40, $37,775.00

Budget number.. DESIGNER APPROVED

Mirrors / Bath Enclosures NWC $11,800.00 $7,129.00 $7,129.00 $0.00 Beehive Glass $7,129.00

BUDGET FROM DESIGNER..
Mirrors Designers budget $1800.00
Shower doors budget only $10,000.00

Tile Tubs / Showers MaCorp $59,681.64 $59,681.64 $59,681.64 $0.00 MaCorp $25,160.89, $32,509.88, $2,010.87

Budget number..

Floors Tile / Stone MaCorp $0.00 $ $ $0.00

Included in tile tubs/showers estimate

Floors Wood MaCorp $66,660.00 $66,660.00 $66,660.00 $0.00 MaCorp $51,047.28, $15,612.72
Gym Rubber Floor MaCorp $2,680.00 $2,680.00 $2,680.00 $0.00 MaCorp $2,680.00
Decking System NWC $15,000.00 $13,844.50 $13,844.50 $0.00 North West Deck Membrane $2,280.00, $8,897.00 FYN $2,667.50

Budget number for weather proofing, deck draining and surface finish..

BBQ Area $ $10,038.00 $10,038.00 $0.00 MaCorp $6,138.00, JRC $3,900.00
Window Tinting Shaded Glass $ $3,022.00 $3,022.00 $0.00
Range Hood A&A Cabinet $ $9,985.00 $9,985.00 $0.00 $1,500.00, Drut $8,485.00
Heat Tape Summit Electric Service $ $11,704.00 $11,704.00 $0.00
Snow Retention North West Roofing $ $11,169.00 $11,169.00 $0.00
Floors Carpet NWC $0.00 $ $ $0.00

Plans show no carpet..

Appliances / Built-in Vacuum MLD $41,807.36 $41,807.36 $41,807.36 $0.00 MLD Deposit $29,429.85, $12,377.51
Appliance Installation MLD $2,775.00 $2,770.30 $2,770.30 $0.00 MLD $2,761.74, 8.56
Flatwork Exterior Material FYN $107,824.00 $107,824.00 $107,824.00 $0.00 Paid = FYN – $27,010.00, $36,000.00 $44,814.00

Labor and material..Budget number only.. Check estimate for what is included in the bid..

Driveway NWC $52,500.00 $84,360.00 $84,360.00 $0.00 FYN – $35,727.00, $16,773.00 OVERAGE FYN $31,860.00

Still need a direction on this to final bid.. 3000 Sq Ft at $17.50 for a budget number on this.

Final / Pre-Landscaping Grading Tycon $0.00 $ $ $0.00

Still need bid for this..

Lightweight Concrete Knell Construction $14,921.00 $14,921.00 $14,921.00 $0.00 Knell Construction $14,921.00
Winter Costs NWC $15,000.00 $990.00 $990.00 $0.00 PAID =$990.00,

Budget number only.. Not sure what will be needed..

Site Control / Clean-up NWC $10,000.00 $9,488.20 $9,488.20 $0.00 $1,425.00, $1,710.00, $1,425.00, $317.84, $2,850.00,$1,045.00, $715.36
Final Clean NWC $10,000.00 $10,000.00 $10,000.00 $0.00 Titan Windows $2,200.00, NWC $1,425.00, CleanTex $2,550.36, Crystal Clean Vents $2,290.00, Susy Chavez $1,534.64
Dumpster NWC $10,800.00 $11,324.75 $11,324.75 $0.00 Honey Bucket $140.00, $27.00, $90.00, $93.00, $884.30, $54.00, $1,318.70, $12.00, $1,673.15, $1,958.75, $938.25, $1,157.45, $1,324.65, $491.90 $548.85, $60.00, $552.75

Budget number for 24 Months..

Chemical Toilet NWC $4,800.00 $ $ $0.00

Budget number for 24 Months..

General Labor NWC $10,000.00 $7,983.93 $7,983.93 $0.00 Saw Jockey $640.00, $1,425.00 BuildworX – $5,130.00. The Home Depot $28.93. NWC $760.00
Monthly Management Fee NWC $72,000.00 $78,000.00 $78,000.00 $0.00 Thru 5/1/25

Estimated 24 months

Hazard Insurance NWC $0.00 $ $ $0.00

Will be figured at the end of the project..

Liability Insurance NWC $0.00 $ $ $0.00

Will be figured at the end of the project..

General Contractor Fee NWC $377,049.57 $414,112.21 $414,112.21 $0.00

GC 10% above cost..

Totals
Final Estimate:

$4,219,551.29

Actual Total-to-Date:

$4,639,532.36

Total Amount Paid:

$4,639,532.36

Current Amount Due:

$0.00

Project Images
Attachments




 

 

Click Here to Print This Page