Projects Test

yourproseo@gmail.com

King / Knight Remodel

Client Name: Brendan Knight and Whitney King

Start Date:
Project Sqft Total:


Project Description:
Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits $0.00 $ $ $0.00

Owner will provide and pay for

Carpentry Rough $9,500.00 $ $ $0.00

Estimated labor and material to re-frame hallway and bedrooms/closets (Two days, two men labor)

Plumbing $15,147.00 $ $ $0.00

Estimated labor and material for plumbing NOTE: This is a budget number for what is known on the job. Any unforeseen plumbing issues that need to be addressed or changed will be done on a time and material basis approved by general contractor and home owner. To add on-demand water and water softener will be $7,500.00 upgrade to estimate

Plumbing Fixtures $0.00 $ $ $0.00

Budget included in Plumbing line item

Electrical / Home Automation $25,000.00 $ $ $0.00

Estimated labor and material for electrical work (budget number). No home automation is included.

Electrical Fixtures $0.00 $ $ $0.00

Homeowner will provide

Heating HVAC $0.00 $ $ $0.00

Mechanical/HVAC unknown until demo is complete

Fireplace Feature Wall $0.00 $ $ $0.00

Not included in budget. Will be determined after final design

Insulation $8,596.00 $ $ $0.00

Estimated material and labor for insulation throughout house

Drywall $10,000.00 $ $ $0.00

Estimated material and labor for sheet rock

Painting Interior $13,450.00 $ $ $0.00

Estimated labor and material for painting

Carpentry Finish $15,289.00 $ $ $0.00

Estimated labor and material for finish carpentry

Closets / Shelving / Built-ins $5,600.00 $ $ $0.00

Estimated labor and material for closet shelving (cost based on paint grade)

Doors Exterior / Interior $6,400.00 $ $ $0.00

Estimated labor and material for exterior doors (3 new fiberglass exterior doors) $4,000.00
Estimated labor and material for interior doors (12 @ 200.00 each) $2,400.00

Railings $5,000.00 $ $ $0.00

Estimated labor and material for interior handrail (cost based on standard wood interior handrail, metal handrail will be an upgrade)

Hardware $0.00 $ $ $0.00

Unknown at this time

Cabinets $35,000.00 $ $ $0.00

Estimated labor and material for cabinets as per walk through (includes master closet)

Demo work, wood flooring, tile work and countertops $67,278.47 $ $ $0.00

Estimated labor and material for demo work, wood floors, tile work, and countertop

Appliances / Built-in Vacuum $9,500.00 $ $ $0.00

Budget Number

Appliance Installation $2,500.00 $ $ $0.00
Site Control / Clean-up $2,500.00 $ $ $0.00
Final Clean $3,500.00 $ $ $0.00
Dumpster $3,500.00 $ $ $0.00

Dumpster and garbage removal

Chemical Toilet $1,500.00 $ $ $0.00
Overhead / General Expenses $12,000.00 $ $ $0.00

Overhead and general expenses ($3,000 per month estimated @ 4 months)

General Contractor Fee $31,103.86 $ $ $0.00

13% fee

Totals
Final Estimate:

$282,364.33

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00