Eatros – 221 Skyridge

Client Name: Morgan Eatros

Start Date: April 1, 2026
Project Sqft Total:


Project Description:

MAIN FLOOR
• LIVING 2,226 SQ. FT.
• GARAGE 875 SQ. FT.
• NON-CONFORMING* 60 SQ. FT.
• PATIO 593 SQ. FT
BASEMENT
• LIVING 2,274 SQ. FT.
• NON-CONFORMING* 1,022 SQ. FT.
• DECK 607 SQ. FT.

Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Wasatch County $0.00 $ $ $0.00
Excavation and Backfill Tycon $0.00 $ $ $0.00

This will have to be addressed as a bid/cost plus line item.. We will need to figure out what has been billed and what is left on the original estimate. I’m sure that there are some item’s that are on the original bid, after the mistakes that were made on the foundation. These items could be what is left for utilities and finishing the backfill, etc.

Footing and Foundation FYN Cuellars $0.00 $ $ $0.00

This will have to be bid out as a fix on the foundation after we start the job. I would have my foundation guy come over first thing and figure that out.

Foundation Weather Proofing NWC $0.00 $ $ $0.00

There may need to be some work done on the foundation after I get it inspected from my weather proofing company. Not sure if the original contractor did it to code or not.

Additional Rebar NWC $5,000.00 $ $ $0.00

This is just a budget number that we may need to finish all the concrete work. It will only be billed if needed.

Foundation Plastering NWC $5,000.00 $ $ $0.00

Budget number to cover any foundation that is still showing after final grading and landscaping is done.

Fill / Gravel Tycon $10,000.00 $ $ $0.00

Additional gravel and road base needed for prepping the driveways, sidewalks and concrete slabs around house.

Steel Beams NWC $70,000.00 $ $ $0.00

I’ll need to see this estimate from the steel company that you have ordered from. THIS IS JUST A BUDGET NUMBER THAT WE TALKED ABOUT.

Steel Connections NWC $5,000.00 $ $ $0.00

Budget number only. It will only be billed if needed.

Material Handling NWC $10,000.00 $ $ $0.00

Budget Number only. It will only be billed if needed. We may need to use some of this line budget item to remove the concrete that has been cut and that still needs to be cut out to fix the foundation.

Lumber Rough Sunpro $96,151.50 $ $ $0.00

Lumber budget number. This price may be less or more depending on what lumber is actually used.

Trusses Sunpro $20,300.00 $ $ $0.00
Carpentry Rough JRC Custom Homes $158,949.00 $ $ $0.00

Look at estimate to see what is included..

Windows / Glass Doors Sierra Pacific $158,188.00 $ $ $0.00

As per Sierra Pacific’s bid..

Exterior Siding Material Sunpro $91,860.55 $ $ $0.00

Wood siding (Material) = $60,401.93
Black painted siding (Hardie board estimate) If we price the wood that was specified it would cost more both in labor and material = $13,188.60
Metal Paneling with hidden fasteners (Labor and Material) = $12,400.00
Shipping and Handling = $5870.02

Masonry FYN Cuellars $142,392.00 $ $ $0.00

Exterior stone..

Soffit / Fascia North West Roofing $54,356.18 $ $ $0.00

Fascia-Sheet Metal (Labor and Material) = $9432
Wood Pre-stained soffit (Material) = $30,180.83
Wood soffit (Labor) = $10,830.00
Shipping and Handling = $3,913.35

Siding Labor Innovative Construction $15,810.60 $ $ $0.00

Wood siding (Labor) = $15,810.60
Black painted siding (Labor included in above price)
Metal Panel siding (Labor included in above price)

Plumbing Most Valuable Plumbing $80,900.00 $ $ $0.00
Plumbing Fixtures Designer $35,889.43 $ $ $0.00

Designer spec’s and pricing.

Electrical / Home Automation Junction Electric $75,000.00 $ $ $0.00

This is a budget number, it may change plus or minus depending on the actual designers spec’s and layout provided after framing.

Electrical Fixtures Designer $37,199.66 $ $ $0.00

Designer spec’s and pricing.

Electronics Junction Electric $55,000.00 $ $ $0.00

Budget per conversation with Morgan from existing bid..

Security System NWC $0.00 $ $ $0.00

No budget for this at this time.

Heating HVAC Paul’s Heating $38,500.00 $ $ $0.00

Check estimate for what is included..

Roofing L & M North West Roofing $71,335.00 $ $ $0.00

NOTE: THINGS THAT STILL NEED A PRICE ON FOR THE ROOF ARE ..
#1 ROOF DRAIN FOR LOW SLOPE ROOF
#2 ROCK OR WHATEVER IS NEEDED TO PLACE ON THE LOW SLOPE ROOF AREA FOR FINISHED LOOK

22 gage metal panel roofing system (Labor and Material) = $65,800.00
TPO Low Slope roof area (Labor and Material) = $5535.00

Fireplaces Alpine Fireplace $9,655.90 $ $ $0.00

Nordik $9,655.90
Callaway $8,349.05

Fireplace Feature Wall FYN Cuellar $25,000.00 $ $ $0.00

THIS WILL HAVE TO BE BID OUT AFTER FRAMING..
This is just a budget number at this time. Will need design from designer and/or owner

Chimney Cap FYN Cuellar $25,000.00 $ $ $0.00

THIS WILL HAVE TO BE BID OUT AFTER FRAMING..
This is just a budget number for the HVAC Vent Caps and the Chimney Cap.

Gutter North West Roofing $12,800.00 $ $ $0.00

Install 6″ seamless 24 guage gutter system plus 200 linear ft of downspout.

Heat Tape Junction Electric $0.00 $ $ $0.00

Not needed for final inspection, but is highly recommended for the area that this house is to be built. The roof drain is a must for safety.. Will be bid at completion of roof system.

Insulation Hansen Insulation $28,956.00 $ $ $0.00
Drywall Torres Drywall $49,600.00 $ $ $0.00
Painting Interior Old Pine Painting $83,355.00 $ $ $0.00

3- Tone paint scheme, stain grade doors, epoxy garage and mechanical
ADDITIONAL PAINT AND STAINING COST FOR ALL ACCENT WALLS, CEILINGS, BUNK BEDS AND BEAMS THROUGHOUT HOUSE. (BILLED AT LABOR AND MATERIAL)

Painting Exterior Innovative Construction $0.00 $ $ $0.00

Touch up on exterior siding included in siding and interior painting bids. The siding and soffit will come pre-stained from factory..

Lumber Finish Sunpro $6,420.00 $ $ $0.00
Carpentry Finish BuildworX $127,452.40 $ $ $0.00

Casing and baseboards – Labor only $34,887.50
Garage hall bench / panel and shelves as designed L&M $2,385.00
Entry T&G ceiling L&M $3,344.50
Bedroom #1 wall treatment panel L&M $2,587.00
Dining Room Beams L&M $14,907.80
Great Room V-groove L&M $6,433.60
Master T&G ceiling L&M $6,499.00
Bunk beds as per design/ two twins over queen with drawers L&M $27,500.00
Bunk room V-Groove wall L&M $10,113.00
Playroom curved daybed with mountain scene bookshelves and drawers L&M $11,750.00
Playroom rock climbing wall / money bars / rope climbing net (material includes: all holds, 11 monkey bars etc) $7,045.00

Closets / Shelving / Built-ins Designer $10,000.00 $ $ $0.00

STILL NEED TO BID THIS.
Need design and type of closets the designer and/or owner would like.. $10,000 Number from Morgan

Doors Exterior / Interior Frontier Woodworks $32,846.77 $ $ $0.00

Frontier Woodworks = $14446.77
High Country Iron Doors (Front door) = $18,400.00 This price includes custom steel door, transom and sidelight..

Garage Door 5 Star $20,318.00 $ $ $0.00

$18,973.00 + (1) side mount opener $65.00
Metal Trim wrap = $1,280.00

Railings J and J $10,075.00 $ $ $0.00

Budget for exterior handrail and interior stair handrail. $155.00 a running foot.. 65′ estimated

Hardware Sunpro $15,000.00 $ $ $0.00

THIS IS A BUDGET NUMBER ONLY… Will need specs from designer and/or owner

Hardware Labor BuildworX $8,000.00 $ $ $0.00

THIS IS A BUDGET NUMBER ONLY… Not knowing what the specs on the hardware will be

Cabinets A&A Cabinets $107,175.00 $ $ $0.00

CLEAR ALDER /PAINT GRADE. ESTIMATE INCLUDES: KITCHEN, PANTRY, LOWER KITCHEN, MUDROOM, LOWER LAUNDRY, MASTER BATH, THEATER, BATH 1,2,3, POWDER BATH AND BUNK BATH

Countertops MaCorp $60,600.00 $ $ $0.00

Price may vary depending on style of slabs that are chosen

Mirrors / Bath Enclosures Designer $15,000.00 $ $ $0.00

THIS IS A BUDGET NUMBER ONLY… Will need specs from designer and/or owner

Floors Tile / Stone MaCorp $73,069.17 $ $ $0.00

Labor and material for all tile throughout house as per designer spec. Rooms to be tiled: powder bath, bath #2, mud room, master bath, lower level laundry, bath #4, bunk bath, and math #3

Floors Wood MaCorp $33,699.00 $ $ $0.00

Labor and material, including stairs with protection covering installed after installation as per designer spec

Wallpaper Designer $0.00 $ $ $0.00

Will need budget and design from designer..

Snowmelt Most Valuable Plumbing $64,000.00 $ $ $0.00

Snowmelt for outside driveway.. Budget number for heated concrete. This may change depending on the actual snowmelt installed.. (Bid for 2000 sq ft heated)

Outside BBQ area and firepit NWC $0.00 $ $ $0.00

These items will be bid after we receive the design and specs from designer and/or owner

Inground Hot Tub NWC $0.00 $ $ $0.00

This item will be bid after we receive the design and specs from designer and/or owner

Steel Awning above garage door NWC $0.00 $ $ $0.00

This item will be bid after we receive the design and specs from designer and/or owner

Snow Retention North West Roofing $15,560.00 $ $ $0.00

This cost has been engineered for this specific roof application. Snow retention has to be installed for the gutters to be under warranty.

RAD coating for main level deck’s RAD Coating $13,961.00 $ $ $0.00

Coating for main level decks..
This is one option out of many. The price may change depending on the option that is chosen.

Floors Carpet MaCorp $10,910.00 $ $ $0.00

Labor and material as per designer spec. Areas to be carpeted: bedrooms, closets and theatre

Appliances / Built-in Vacuum Mountain Land $65,000.00 $ $ $0.00

Will need budget from designer.. Number from Morgan

Appliance Installation Mountain Land $0.00 $ $ $0.00

Will need budget from designer..

Flatwork Exterior Labor FYN Cuellar $63,380.50 $ $ $0.00

This is a budget number for labor and material. See estimate to see what is included (garage floor, back patio, front porch, driveway with concrete and paver 2′ edge around driveway) Price may vary depending on the actual sq ft poured.

Driveway FYN Cuellar $0.00 $ $ $0.00

Included in Flatwork Exterior line idea..

Final / Pre-Landscaping Grading Tycon $0.00 $ $ $0.00

Will be part of the updated excavation bid and budget.

Winter Costs NWC $0.00 $ $ $0.00

ONLY IF NEEDED..

Landscaping Altitude Maintenance $65,000.00 $ $ $0.00

BUDGET ONLY.. WE NEED TO DESIGN AND BID THIS OUT FOR A TRUE NUMBER..

Site Control / Clean-up NWC $10,000.00 $ $ $0.00

Day to day job site control and cleaning.

Final Clean NWC $10,000.00 $ $ $0.00

Budget only, but should cover duct cleaning, window cleaning and final construction cleaning.

Dumpster NWC $7,500.00 $ $ $0.00
Chemical Toilet NWC $5,000.00 $ $ $0.00
General Labor NWC $15,000.00 $ $ $0.00

Miscellaneous labor that may be needed for project

Liability Insurance $0.00 $ $ $0.00

Homeowner is required to obtain their own course of construction liability insurance.

General Contractor Fee NWC $256,978.22 $ $ $0.00

11% above cost of construction. If awarded this job and also your brother’s house, the fee will be lowered to 12% for both jobs.

Totals
Final Estimate:

$2,593,143.88

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00