Oakley Spec (Herbert Plan)

Client Name: No Worries Development Group

Start Date:
Project Sqft Total: 5500


Project Description:
Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits Various $30,000.00 $ $ $0.00

Building Permit $25,000

Excavation and Backfill Tycon $60,000.00 $ $ $0.00
Footing and Foundation FYN $129,000.00 $ $ $0.00
Foundation Weather Proofing Rocky Mtn Waterproofing $2,250.00 $ $ $0.00
Additional Rebar FYN $2,750.00 $ $ $0.00
Fill / Gravel FYN $2,750.00 $ $ $0.00
Steel Connections J&J Fabrication $3,850.00 $ $ $0.00
Material Handling NWC $7,950.00 $ $ $0.00
Lumber Rough Sunpro $165,680.00 $ $ $0.00
Trusses Sunpro $47,200.00 $ $ $0.00
Carpentry Rough JRC $130,000.00 $ $ $0.00
Windows / Glass Doors Sierra Pacific $74,000.00 $ $ $0.00
Exterior Siding Material Innovative Construction $71,000.00 $ $ $0.00
Masonry FYN $109,000.00 $ $ $0.00
Soffit / Fascia North West Roofing $27,600.00 $ $ $0.00
Siding Labor Innovative Construction $0.00 $ $ $0.00
Plumbing MVPH $34,000.00 $ $ $0.00
Plumbing Fixtures MVPH $11,000.00 $ $ $0.00
Electrical / Home Automation Junction $88,850.00 $ $ $0.00
Electrical Fixtures $11,000.00 $ $ $0.00
Electronics $0.00 $ $ $0.00
Heating HVAC Paul’s Heating $42,850.00 $ $ $0.00
Roofing L & M North West Roofing $57,400.00 $ $ $0.00

Metal included

Fireplaces Alpine Fireplace $21,125.00 $ $ $0.00
Fireplace Feature Wall $22,000.00 $ $ $0.00
Chimney Cap $0.00 $ $ $0.00
Gutter North West Roofing $7,610.00 $ $ $0.00
Heat Tape Summit Electric $0.00 $ $ $0.00
Insulation Hansen Insulation $36,270.00 $ $ $0.00
Drywall Torres Drywall $54,000.00 $ $ $0.00
Painting Interior MC Baldwin $86,100.00 $ $ $0.00
Painting Exterior MC Baldwin $7,150.00 $ $ $0.00
Lumber Finish Sunpro $50,000.00 $ $ $0.00
Carpentry Finish BuildworX $56,000.00 $ $ $0.00
Closets / Shelving / Built-ins BuildworX $13,200.00 $ $ $0.00
Doors Exterior / Interior Frontier Woodworks $26,300.00 $ $ $0.00
Garage Door 5 Star Building $30,000.00 $ $ $0.00
Railings J&J Fabrication $9,350.00 $ $ $0.00
Wood Ceilings / Wood Walls / Wood Columns / Etc… BuildworX $0.00 $ $ $0.00
Hardware Sunpro $4,950.00 $ $ $0.00
Hardware Labor BuildworX $4,950.00 $ $ $0.00
Cabinets A&A Cabinet $141,350.00 $ $ $0.00
Countertops MaCorp $43,450.00 $ $ $0.00
Mirrors / Bath Enclosures $12,320.00 $ $ $0.00
Tile Tubs / Showers MaCorp $80,150.00 $ $ $0.00
Floors Wood MaCorp $47,010.00 $ $ $0.00
Radon Gas System $9,075.00 $ $ $0.00
Well Legend Drilling $50,000.00 $ $ $0.00
Green Belt Fees Summit County $20,000.00 $ $ $0.00
Utilities to home Rocky Mtn Power $0.00 $ $ $0.00
Asphalt $0.00 $ $ $0.00
SWPPP $0.00 $ $ $0.00
Floors Carpet MaCorp $14,300.00 $ $ $0.00
Appliances / Built-in Vacuum MLD $48,000.00 $ $ $0.00
Appliance Installation MLD $3,340.00 $ $ $0.00
Flatwork Prep FYN $5,500.00 $ $ $0.00
Flatwork Exterior Material FYN $47,480.00 $ $ $0.00
Driveway MaCorp $14,080.00 $ $ $0.00
Final / Pre-Landscaping Grading Tycon $0.00 $ $ $0.00
Winter Costs NWC $3,300.00 $ $ $0.00
Landscaping Altitude $0.00 $ $ $0.00
Site Control / Clean-up NWC $11,000.00 $ $ $0.00
Final Clean All We Can Do $5,500.00 $ $ $0.00
Dumpster Honey Bucket $6,600.00 $ $ $0.00
Chemical Toilet Honey Bucket $3,500.00 $ $ $0.00
General Labor NWC $11,000.00 $ $ $0.00
Monthly Management Fee NWC $45,000.00 $ $ $0.00

Estimated 15 months

Hazard Insurance $0.00 $ $ $0.00
Totals
Final Estimate:

$2,159,090.00

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00