Colton Christensen Residents / Garage

Client Name: Colton

Start Date:
Project Sqft Total: 2100


Project Description:
Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Excavation and Backfill Tycon Construction $33,000.00 $ $ $0.00 Check bid for whats included
Footing and Foundation C&S concrete special, inc $30,670.50 $ $ $0.00
Lumber Rough SunPro $29,500.00 $ $ $0.00 Trusses ($5,618.75)
Carpentry Rough Casey Page $23,500.00 $ $ $0.00
Windows / Glass Doors SunPro $12,468.45 $ $ $0.00
Exterior Siding Material Wall to Wall $18,675.00 $ $ $0.00
Soffit / Fascia Wall to wall $2,464.00 $ $ $0.00
Siding Labor Wall to Wall $1.00 $ $ $0.00
Plumbing MVPH $9,150.00 $ $ $0.00
Plumbing Fixtures MVPH $3,800.00 $ $ $0.00
Electrical / Home Automation Pauls Electric Service $12,000.00 $ $ $0.00
Electrical Fixtures Owner Provided $2,500.00 $ $ $0.00
Heating HVAC Pauls Heating $8,650.00 $ $ $0.00 look at bids for gas hook ups included in bid
Fire Sprinklers Fire Services $9,550.00 $ $ $0.00
Roofing L & M North West roofing $16,645.50 $ $ $0.00
Fireplaces Alpine fireplace $4,000.00 $ $ $0.00 check for bids for option #2 cheaper fire place
Gutter Wall to Wall $1,585.00 $ $ $0.00
Insulation Premier building supply $8,535.00 $ $ $0.00
Drywall RCE Drywall $11,800.00 $ $ $0.00
Painting Interior MC Baldwin Painting $12,600.00 $ $ $0.00 Bid for painting is for 2100 sq ft at $6.00 per foot
Lumber Finish Wasatch Group $8,000.00 $ $ $0.00
Carpentry Finish SunPro $6,300.00 $ $ $0.00
Closets / Shelving / Built-ins Wasatch Group $2,500.00 $ $ $0.00
Doors Exterior / Interior SunPro $9,700.00 $ $ $0.00
Railings SunPro $5,600.00 $ $ $0.00 Material ($3100.00) labor ($2500.00)
Hardware SunPro $2,000.00 $ $ $0.00
Cabinets Summit Cabinets $19,050.00 $ $ $0.00
Countertops McCorp $11,000.00 $ $ $0.00
Mirrors / Bath Enclosures Owner Provide $3,000.00 $ $ $0.00
Tile Tubs / Showers McCorp $6,100.00 $ $ $0.00
Floors Tile / Stone McCorp $2,800.00 $ $ $0.00
Floors Wood McCorp $7,500.00 $ $ $0.00
Other garage option Roper builders $26,126.20 $ $ $0.00
Site Prep… Owner Provided $3,000.00 $ $ $0.00
$ $ $ $0.00
Floors Carpet Terry M…. $3,500.00 $ $ $0.00
Appliances / Built-in Vacuum Owner Provided $8,000.00 $ $ $0.00
Appliance Installation Owner Provided $1,500.00 $ $ $0.00
Flatwork Exterior Material Owner Provided $3,000.00 $ $ $0.00
Final Clean Owner Provided $1,500.00 $ $ $0.00
Dumpster Honey Bucket $2,500.00 $ $ $0.00
Chemical Toilet Honey Bucket $1,500.00 $ $ $0.00
Totals
Final Estimate:

$385,270.65

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00