Barn…
Client Name: Rick Shapiro
Start Date:
Project Sqft Total:
Project Description:
Budget Breakdown
| Description | Vendor (Private) | Estimated Cost | Actual Cost | Current Paid | Amount Due | Notes (Private) | Description |
|---|---|---|---|---|---|---|---|
| Planning and Permits | Oakley City | $0.00 | $ | $ | $0.00 |
I still need an answer from the city on what is required… |
|
| Excavation and Backfill | Tycon | $5,000.00 | $ | $ | $0.00 | ||
| Footing and Foundation | Wasatch Group | $5,500.00 | $ | $ | $0.00 |
384 Sq.Ft. of Flatwork with footing.. Labor and Material |
|
| Fill / Gravel | Tycon | $0.00 | $ | $ | $0.00 |
Included.. |
|
| Lumber Rough | SunPro | $19,136.85 | $ | $ | $0.00 |
This includes sheeting the interior walls also.. Material |
|
| Carpentry Rough | Wasatch Group | $9,800.00 | $ | $ | $0.00 |
Installing windows included.. and sheeting the interior walls.. |
|
| Windows / Glass Doors | SunPro | $2,400.00 | $ | $ | $0.00 | ||
| Exterior Siding Material | SunPro | $13,000.00 | $ | $ | $0.00 |
Random Board and Bat to match existing buildings.. |
|
| Soffit / Fascia | Wasatch Group | $2,100.00 | $ | $ | $0.00 |
White Soffit and Fascia to match existing buildings.. |
|
| Siding Labor | Wasatch Group | $6,600.00 | $ | $ | $0.00 | ||
| Plumbing | Tycon | $0.00 | $ | $ | $0.00 |
Outside faucet ran over to new barn.. Included |
|
| Electrical / Home Automation | Pauls Electric Service | $8,500.00 | $ | $ | $0.00 |
Bid includes running power from existing building to new barn.. All Labor and Material.. Also includes electric heater.. |
|
| Electrical Fixtures | NWC | $1,500.00 | $ | $ | $0.00 |
3- Barn lights to match existing lights on buildings.. |
|
| Roofing L & M | NWC | $6,500.00 | $ | $ | $0.00 |
This bid is for labor and material.. Material for the roof will be metal roofing that will rust to match existing buildings.. |
|
| Insulation | Pick’s | $5,000.00 | $ | $ | $0.00 |
bid includes batting the walls and the ceiling.. |
|
| Painting Exterior | Baldwin Painting | $1,500.00 | $ | $ | $0.00 |
Bid includes painting the front timbers white to match existing buildings.. |
|
| Doors Exterior / Interior | NWC | $3,000.00 | $ | $ | $0.00 |
Material and labor to build 3 barn doors.. |
|
| Hardware | NWC | $1,500.00 | $ | $ | $0.00 | ||
| Tyvek or Building Weather barrier | NWC | $1,500.00 | $ | $ | $0.00 |
Material and labor |
|
| $ | $ | $ | $0.00 | ||||
| Site Control / Clean-up | NWC | $1,500.00 | $ | $ | $0.00 | ||
| Final Clean | NWC | $1,500.00 | $ | $ | $0.00 | ||
| Dumpster | NWC | $1,000.00 | $ | $ | $0.00 | ||
| Chemical Toilet | NWC | $600.00 | $ | $ | $0.00 | ||
| General Contractor Fee | NWC | $14,570.53 | $ | $ | $0.00 |
Totals
Final Estimate:$111,707.38 |
Actual Total-to-Date:$0.00 |
Total Amount Paid:$0.00 |
Current Amount Due:$0.00 |