Porter Family Residence

Client Name: Brain and Mandy Porter

Start Date:
Project Sqft Total:


Project Description:
Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Planning and Permits CDS $15,000.00 $ $ $0.00

Owner will pay…

Excavation and Backfill Tycon $26,112.75 $ $ $0.00

Review bid for what is included…

Footing and Foundation C&S $31,100.00 $ $ $0.00

Bid good for 90 days as of 3/10/2021… May go up…

Foundation Weather Proofing Rocky Mtn. weather proofing $2,500.00 $ $ $0.00
Fill / Gravel Tycon $0.00 $ $ $0.00

Included in Tycon’s Excavation bid….

Lumber Rough SunPro $70,000.00 $ $ $0.00
Trusses SunPro $52,799.61 $ $ $0.00
Carpentry Rough Casey’s Framing $39,000.00 $ $ $0.00
Windows / Glass Doors Sierra Pacific $23,300.00 $ $ $0.00

White o White casements… Bid Is for White on White.. Includes labor to install..NOTE: FOR BLACK ADD $6,500.00

Exterior Siding Material Garcia Plastering $40,000.00 $ $ $0.00

Review bid to see what’s included…

Masonry FYN $0.00 $ $ $0.00

Review bid to see what’s included… Interior and Exterior

Soffit / Fascia Garcia Plastering $0.00 $ $ $0.00

Included in siding bid…

Plumbing MVPH Inc.. $19,980.00 $ $ $0.00

Review Bid…

Plumbing Fixtures MVPH Inc.. $0.00 $ $ $0.00

Included in Plumbing bid…

Electrical / Home Automation Paul’s Electric service $24,972.50 $ $ $0.00

NO GC FEE ADDED…

Electrical Fixtures NWC $0.00 $ $ $0.00

Budget Only…

Electronics Pauls Electric Service $2,500.00 $ $ $0.00
Heating HVAC Pauls Heating.. $18,700.00 $ $ $0.00

Review bid for what’s included…

Roofing L & M North West Roofing $17,680.94 $ $ $0.00
Fireplaces Alpine fireplace $5,500.00 $ $ $0.00

Budget for 1 fireplaces…

Gutter North West Roofing $4,000.00 $ $ $0.00
Insulation Picks Insulation $16,418.00 $ $ $0.00
Drywall Torres Drywall $22,200.00 $ $ $0.00
Painting Interior MC Baldwin Painting $20,345.00 $ $ $0.00

Review bid for what’s included…

Painting Exterior Garcia Plastering $0.00 $ $ $0.00

Included in siding Bid…

Lumber Finish SunPro $3,600.00 $ $ $0.00
Carpentry Finish Wasatch Group $11,700.00 $ $ $0.00
Closets / Shelving / Built-ins Wasatch Group $0.00 $ $ $0.00

Labor and Material…

Doors Exterior / Interior SunPro $9,800.00 $ $ $0.00
Garage Door Five Star $6,500.00 $ $ $0.00
Hardware SunPro $4,000.00 $ $ $0.00

budget includes Labor and material…

Cabinets Summit Cabinet $26,000.00 $ $ $0.00

Budget only…

Countertops MaCorp $10,000.00 $ $ $0.00

Budget number only…

Mirrors / Bath Enclosures Beehive glass $2,600.00 $ $ $0.00

Budget number only…

Tile Tubs / Showers McCorp $15,000.00 $ $ $0.00

Budget for house tile work.. Review bid for budget…

Floors Tile / Stone McCorp $0.00 $ $ $0.00

Included in tile bid…

Floors Wood McCorp $8,000.00 $ $ $0.00

Budget number only…

Floors Carpet Ground Zero $5,100.00 $ $ $0.00

Budget only… 170 Yards @ $30.00 a yard

Appliances / Built-in Vacuum NWC $10,000.00 $ $ $0.00

Budget number only…

Appliance Installation MyTy… $1,500.00 $ $ $0.00

Budget only…

Flatwork Exterior Material FYN $12,987.00 $ $ $0.00

Review bid to see what’s included…

Flatwork Exterior Labor FYN $0.00 $ $ $0.00

Included in Flatwork bid…

Driveway FYN $0.00 $ $ $0.00

Included in Flatwork bid…

Site Control / Clean-up NWC $6,000.00 $ $ $0.00

Includes site and foundation survey’s

Final Clean NWC $2,000.00 $ $ $0.00

Budget only…

Dumpster NWC $2,500.00 $ $ $0.00
Chemical Toilet Honey bucket $2,500.00 $ $ $0.00
General Labor NWC $5,000.00 $ $ $0.00
General Contractor Fee NWC $57,280.00 $ $ $0.00

10% GC Fee…

Totals
Final Estimate:

$654,175.80

Actual Total-to-Date:

$6,500.00

Total Amount Paid:

$0.00

Current Amount Due:

$6,500.00

Project Images
Attachments




 

 

Click Here to Print This Page