New house in Oakley

Client Name: Kent and DeAnn Woolstenhulme

Start Date: June 1, 2021
Project Sqft Total:


Project Description:
Budget Breakdown
Description Vendor (Private) Estimated Cost Actual Cost Current Paid Amount Due Notes (Private) Description
Masonry FYN $20,000.00 $ $ $0.00

Finish Exterior rock and inside fireplace and kitchen wall..

Soffit / Fascia North West Roofing $18,426.78 $ $ $0.00
Plumbing MVP&H $10,000.00 $ $ $0.00

Labor for finish..

Plumbing Fixtures MVP&H $14,000.00 $ $ $0.00

Finish fixtures..

Electrical / Home Automation Pauls Electric Service $7,500.00 $ $ $0.00

Finish Material..

Electrical Fixtures Pauls Electric Service $14,000.00 $ $ $0.00
Heating HVAC Pauls Heating $3,600.00 $ $ $0.00

Finish Heating and AC..

Roofing L & M North West Roofing $29,208.26 $ $ $0.00
Chimney Cap J Bar J $5,000.00 $ $ $0.00
Gutter North West Roofing $5,638.00 $ $ $0.00
Insulation Picks $21,017.00 $ $ $0.00
Drywall Torras Drywall $34,500.00 $ $ $0.00
Lumber Finish SunPro $25,000.00 $ $ $0.00

Includes Interior doors..

Carpentry Finish Wasatch $25,000.00 $ $ $0.00
Garage Door 5 Star Products $17,500.00 $ $ $0.00
Railings J and J Fab.. $25,500.00 $ $ $0.00
Hardware SunPro $7,500.00 $ $ $0.00
Cabinets Summit Cabinets $38,420.50 $ $ $0.00
Mirrors / Bath Enclosures NWC $7,500.00 $ $ $0.00
Tile Tubs / Showers McCorp $56,849.24 $ $ $0.00
Floors Wood NWC $7,702.32 $ $ $0.00
Floors Carpet Sub Zero $6,500.00 $ $ $0.00
Appliances / Built-in Vacuum Mountain Land $21,252.90 $ $ $0.00
Totals
Final Estimate:

$421,615.00

Actual Total-to-Date:

$0.00

Total Amount Paid:

$0.00

Current Amount Due:

$0.00

Project Images
Attachments




 

 

Click Here to Print This Page